Inve US ▾
PPPPL

PPL (PPL) Q2 FY26 earnings call: guidance and Q&A

Earnings call· Jun 2026 (Q2 FY26)· Utilities· Aug 7, 2026

Source: earnings call transcript

Executive summary

PPL Q2 FY26 — Strong Execution and Visible Long-Term Growth from Data Centers and Invitium JV

PPL delivered solid Q2 FY26 results, reaffirming its full-year earnings forecast and long-term financial targets, driven by disciplined execution and constructive regulatory outcomes. The company is building significant future growth opportunities through accelerating data center demand in Pennsylvania and Kentucky, supported by robust large-load tariffs and the Invitium Energy joint venture, which is progressing towards commercial agreements by year-end.

Highlights

5
  • Reported Q2 FY26 ongoing earnings of $0.33 per share, in line with expectations and reaffirming the full-year forecast.

  • Secured constructive regulatory outcomes in Pennsylvania, with a $275 million rate increase effective July 1, and Rhode Island, with new rates expected September 1.

  • Pennsylvania service territory saw data center agreements increase to 32 GW, with over 11 GW now under financially committed Electric Services Agreements (ESAs).

  • Kentucky's economic development pipeline expanded to 13.7 GW of potential load growth, with probability-weighted projections for 3.7 GW new load by 2032.

  • Invitium Energy JV progressed with strategic land sites for 8-14 GW and over 5 GW in the PJM interconnection queue, targeting 1 or more commercial agreements by year-end.

Concerns

3
  • Kentucky segment results were flat YoY due to lower sales volumes from less favorable weather, higher operating costs, depreciation, and interest expense.

  • Pennsylvania Regulated segment results decreased by $0.01 per share YoY primarily due to higher depreciation and interest expense.

  • The PJM capacity matching process and auction caps are currently below cost of new entry, potentially impacting Invitium's participation in the auction.

Guidance & targets

CategoryTargetConfidence
Ongoing Earnings Forecast
$1.90 to $1.98 per share
high materiality
High
Capital Investments
approximately $5 billion
high materiality
High
Capital Investments
$23 billion
high materiality
High
Annual EPS Growth
6% to 8%
high materiality
High
Annual Dividend Growth
4% to 6%
medium materiality
High
FFO to Debt
16% to 18%
medium materiality
High
Invitium JV Earnings Contribution
not material
low materiality
High
Invitium JV Earnings Contribution (Shorter Lead Time Technologies)
could begin contributing earnings
medium materiality
Medium
Invitium JV Earnings Contribution (CCGTs)
more meaningful earnings and cash flows
high materiality
Medium
Invitium JV Commercial Agreements
1 or more
medium materiality
High
Kentucky Incremental Investment
$3.5 billion to $4 billion
high materiality
Medium

Segment performance

SegmentRevenueYoYQoQMargin
Kentucky
Results were flat compared to Q2 2025, driven by higher base rate recovery offset by lower sales volumes, higher operating costs, depreciation, and interest expense.
Higher base rate recovery: due to higher retail rates effective January 1Lower sales volumes: due to less favorable weatherHigher operating costsHigher depreciation expenseHigher interest expense
—flat——
Pennsylvania Regulated
Results were $0.01 lower compared to Q2 2025, primarily due to higher depreciation and interest expense, partially offset by higher transmission revenue.
Higher depreciation expenseHigher interest expenseHigher transmission revenue: from additional capital investments
—$0.01 lower——
Rhode Island
Results increased by $0.02 compared to Q2 2025, driven by higher rider revenue and lower operating costs, partially offset by higher depreciation expense.
Higher rider revenueLower operating costsHigher depreciation expense
—$0.02 higher——
Corporate and Other
Results remained flat compared to Q2 2025, mainly due to higher interest expense offset by other non-significant factors.
Higher interest expense
—flat——

Orderbook & backlog

Data Center Agreements 32 GW Q2 FY26

3.5 GW increase from last quarter

Includes all signed agreements in Pennsylvania service territory.

Data Center Agreements under ESAs >11 GW Q2 FY26

>1 GW increase from last quarter

Electric Services Agreements (ESAs) in Pennsylvania carry meaningful financial commitments from the customer.

Data Center Agreements under Construction >6.5 GW Q2 FY26

Projects in Pennsylvania have entered the construction phase.

Kentucky Economic Development Pipeline 13.7 GW Q2 FY26

800 MW increase from last quarter

Includes 11.6 GW data center demand and 2.1 GW manufacturing/other non-data center projects.

Kentucky Economic Development Pipeline under Reimbursement Agreements 1.3 GW Q2 FY26

up from 900 MW in Q1

Supported by signed reimbursement agreements.

Kentucky Probability-Weighted New Load 3.7 GW Q2 FY26

more than double the amount in 2025 CPCN filing

Expected new load by 2032.

Deals & partnerships

Blackstone Joint venture to develop new generation resources to serve large load customers, particularly data centers. long-term

Invitium Energy, our joint venture with Blackstone, represents meaningful long-term earnings and cash flow upside beyond the current plan. We now have strategic land sites capable of supporting between 8 and 14 gigawatts of new generation... We have over 5 gigawatts of new CCGT generation that has been accepted in the PJM interconnection queue. We also have over 5 gigawatts of reservation agreements for combined cycle gas turbines.

Capital programs

2026 Capital Investment Plan underway $5 billion
Period spend: $2.3 billion
Spent to date: $2.3 billion
Start: FY26

Benefit:Strengthen safety and reliability of networks; progress on generation projects in Kentucky

We are on pace to deploy approximately $5 billion of capital investments in 2026 to support the delivery of safe, reliable, and affordable energy service. We've also made great progress on our CapEx program and have deployed approximately $2.3 billion through the end of the second quarter.

Multi-Year Capital Investment Plan underway $23 billion
Start: current

Benefit:Support average annual rate base growth of over 10%

Longer term, we continue to project $23 billion of capital investment needs through 2029, supporting average annual rate base growth of over 10%.

Invitium Energy JV Generation Development underway $12.5 billion to $15 billion
Funding: PPL's share 51%; construction period type financing structures; permanent financing post-COD
Start: current

Benefit:5 GW of new CCGT generation

Using the market consensus project cost of approximately $2,500 to $3,000 per KW, that 5 gigawatts represents between $12.5 billion and $15 billion of potential future investment through 2032, of which PPL's share would be 51%... during the construction period, we'll use construction period type financing structures that will keep the balance sheet to limit any near-term dilution -- and then once those projects go COD, we'll put in place a permanent financing structure...

Kentucky Incremental Generation Resources planned $3.5 billion to $4 billion
Start: 2027

Benefit:266 MW Lewis Ridge pumped storage, 400 MW batteries, additional natural gas combined cycle generation

those projects represent an incremental $3.5 billion to $4 billion of potential investment to be incurred between 2027 and 2032.

Risks & headwinds

Kentucky Rate Case Reconsideration decision from KPSC by August 14

some flaws in that decision

Mitigation:Appreciate the commission's thoughtful review... continue to believe the investments and mechanisms supporting this filing are important.

PJM Capacity Auction Caps current

well below cone

Mitigation:Focus continues to be on the bilateral contracting process directly with our customer base.

Legislative Scrutiny on Data Centers current

quite a bit of activity prior to the budget being approved

Mitigation:PPL's large-load tariffs protect existing customers; engaging with local communities; developers shifting to more transparent engagement and community benefit packages.

Hyperscaler-Owned Batteries by 2029

some of that could be owned directly by the hyperscalers

Mitigation:Invitium offers a full suite of assets; engages with hyperscalers on technology choices and ramp curves.

What to watch in Q3 FY26

Kentucky Rate Case Reconsideration Decision

By August 14
Current Awaiting KPSC decision on reconsideration request.
Target Favorable decision by KPSC.

Why it matters

Will impact Kentucky segment earnings and regulatory certainty for future investments.

In Kentucky, we're awaiting the commission's decision on our reconsideration request following another thorough and constructive regulatory process... We've requested a decision from the KPSC by August 14.

Find out whether PPL delivers this. Inve re-checks your case every morning.

Q&A highlights

Will Invitium need to wait for PJM procurement, or can deals be announced independently and included later?

PPL is actively negotiating bilaterally, independent of the PJM RBP process. They submitted proposals to PJM to maximize customer contacts but bilateral contracting is the primary path.

“So our ability to get to closure on bilateral contracts is irrespective of the PJM process.”

asked by Michael Lonegan · answered by Vincent Sorgi

3 min read 7 chapters

Detailed narrative

Q2 Performance and Outlook Reaffirmation

PPL reported Q2 FY26 ongoing earnings of $0.33 per share, aligning with expectations. The company reaffirmed its full-year 2026 ongoing earnings forecast of $1.90 to $1.98 per share, with a midpoint of $1.94, anticipating stronger earnings in the second half due to rate case outcomes.

Long-term financial targets, including 6% to 8% annual EPS growth through 2029 and 4% to 6% annual dividend growth, were also reaffirmed.

Regulatory Progress and Constructive Outcomes

PPL achieved significant regulatory progress, with base rate cases underway in all three primary jurisdictions. In Pennsylvania, PPL Electric's rate case settlement became effective July 1, approving a $275 million increase and including a 2-year stay-out provision. Rhode Island's base rate case is on track, with new rates expected September 1, and the company is pursuing a Hold Harmless Bill Credit proposal to offset rate increases.

Kentucky is awaiting a decision on a reconsideration request by August 14.

Accelerating Data Center Demand in Pennsylvania

The Pennsylvania service territory continues to experience strong data center activity, with signed agreements increasing to 32 GW, a 3.5 GW rise from last quarter. Over 11 GW are now under Electric Services Agreements (ESAs) with meaningful financial commitments. More than 6.5 GW are under construction, and two data centers began taking utility service in Q2, expected to ramp to 2 GW of load by 2031.

Invitium Energy Joint Venture Progress

The Invitium JV with Blackstone is moving from concept to execution, securing strategic land sites capable of supporting 8 to 14 GW of new generation and over 5 GW of CCGT generation accepted into the PJM interconnection queue. This represents a potential $12.5 billion to $15 billion investment through 2032 (PPL's share 51%).

The JV is expected to have one or more commercial agreements by year-end, with potential earnings contributions from shorter lead time technologies by 2029-2030.

Kentucky's Emerging Growth Platform

Kentucky is becoming a significant platform for incremental growth, with its economic development pipeline expanding to 13.7 GW of potential load, including 11.6 GW from data centers. Approximately 1.3 GW is now supported by signed reimbursement agreements. Probability-weighted projections indicate 3.7 GW of new load by 2032, more than double the previous forecast, potentially leading to a CPCN filing for additional generation resources by year-end, representing $3.5 billion to $4 billion of investment between 2027 and 2032.

Large-Load Tariffs and Customer Protection

PPL highlighted the effectiveness of its large-load tariffs in Pennsylvania and Kentucky, designed to ensure "growth pays for growth" and protect existing customers. These tariffs require long contracts (10-15 years), guaranteed payments of at least 80% of reserved capacity, upfront collateral, and material termination fees.

In Pennsylvania, large-load customers will contribute $11 million annually to low-income assistance, and existing customers could see transmission bill reductions of ~$25/month if 31.8 GW of advanced-stage projects are realized.

PJM Market Dynamics and Bilateral Contracting

Management noted that PJM's recent FERC proposal and the RBP process are pushing towards bilateral contracting for new generation development. While PPL submitted proposals for the matchmaking process, the company's primary focus remains on bilateral agreements with customers, as PJM auction caps are currently below the cost of new entry for certain assets.

The company is running development work in parallel with customer negotiations to respond quickly.

Summary of the company's earnings call; see how call summaries are prepared. Not investment advice.