Skip to content

    KNR Construct.

    KNRCONMixed
    Construction·20 Nov 2025
    Management Summary

    KNR Constructions reported a consolidated revenue of INR 646 crores for Q2 FY26, with an EBITDA margin of 29.8% and a net profit of INR 105 crores. The company's order book stood at INR 8,748 crores as of September 30, 2025, with a target to secure INR 8,000-10,000 crores in new orders by FY26 end. Management acknowledged a challenging period for order inflows and execution, citing monsoon impacts and NHAI delays, but anticipates a pickup in H2 FY26 with a revenue guidance of INR 800-900 crores.

    Highlights

    8
    • Q2 FY26 Consolidated Revenue: INR 646 crores

    • Q2 FY26 Consolidated EBITDA: INR 192 crores, with a margin of 29.8%

    • Q2 FY26 Consolidated Net Profit: INR 105 crores

    • Total Order Book (as of Sep 30, 2025): INR 8,748 crores

    • Target Order Inflow for FY26: INR 8,000 crores to INR 10,000 crores

    • Consolidated Net Debt (as of Sep 30, 2025): INR 2,338 crores

    • Net Debt to Equity (consolidated, as of Sep 30, 2025): 0.49x

    • H2 FY26 Revenue Guidance: INR 800-900 crores

    Concerns

    3
    • Sluggish Project Awarding Activity

    • Land Acquisition Delays

    • Significant Irrigation Project Receivables

    What Changed1

    vs Q3 FY26

    Guidance items15 → 14 (-1)

    Key financials

    Single quarter

    07 metrics
    1. 01Consolidated Revenue₹646 Cr
    2. 02Consolidated EBITDA₹192 Cr
    3. 03Consolidated EBITDA Margin29.8%
    4. 04Consolidated PAT₹105 Cr
    5. 05Order Book₹8,748 Cr

    Segment breakdown

    Order Book Bifurcation
    29% Road Projects18% Irrigation Projects12% Pipeline Project41% Mining Project
    Q2 FY26 Segmental Revenue
    29% HAM34% EPC Roadwork36% Irrigation100% Back-to-back
    List

    Guidance & targets

    14
    CategoryTargetPriority
    Order Inflow
    Total Order Inflow
    INR8,000 crores to INR10,000 crores
    Medium
    Order Inflow
    Bhandara-Gadchiroli LOA
    Q4
    Medium
    Revenue
    Total Revenue
    INR800 crores to INR900 crores
    Medium
    Revenue
    Pipeline Project Revenue Certification
    INR150 crores to INR200 crores
    High
    Revenue
    Pipeline Project Revenue
    around INR300 crores to INR350 crores
    Medium
    Revenue
    Mining Project Development Work
    around INR90 crores
    Medium
    Revenue
    Mining Project Operation Period Revenue
    INR300 crores to INR400 crores
    Medium
    Revenue
    Mysore Projects Revenue
    around INR300 crores
    Medium
    Revenue
    Mysore Projects Revenue
    around INR600 crores to INR700 crores
    Medium
    Revenue
    Irrigation Unbilled Revenue Booking
    around INR300 crores to INR350 crores
    Medium
    Revenue
    Irrigation Unbilled Revenue Booking
    around INR600 crores to INR700 crores
    Medium
    Profitability
    EBITDA Margin
    13% to 14%
    Medium
    Sector Outlook
    NHAI Kilometers Awarded
    3,000 kilometers
    Medium
    Capex
    Capital Expenditure
    around INR30 crores to INR40 crores
    High

    Risks & concerns

    6
    RiskSeverity

    Sluggish Project Awarding Activity

    MoRTH and NHAI project awarding activity has been relatively slow, impacting order book conversion.Management acknowledged

    high

    Execution Delays due to Monsoon

    Execution activities were muted during the quarter due to extended monsoon conditions across several parts of the country.Management acknowledged

    medium

    State Government Payment Risks

    State government projects carry inherent risks with payments, which is a constant consideration.Management acknowledged

    medium

    Land Acquisition Delays

    Mining project and Kushalnagara HAM project are facing delays due to land acquisition issues and local demands for service roads.Management acknowledged

    high

    Significant Irrigation Project Receivables

    Around INR758 crores in irrigation receivables (out of INR1,090 crores total debtors) are outstanding, with INR670 crores for Package 4 certified but not yet paid.Management acknowledged

    high

    Areas of Evasion(1)

    • Exact timeline for resolution and payment of irrigation receivables.

    Q&A highlights

    3

    “Right now, it is quite difficult to say anything, sir. But however, I'll try to answer it this way, that INR800 crores to INR900 crores will be there in this second half of this year, that will be there. And upcoming, I think we are expecting good order inflow to come.”

    Addresses the critical investor concern about future revenue visibility given the current low order book and slow execution pace.

    asked by Shravan Shah

    3 min read7 chapters

    Detailed Narrative

    01

    Q2 FY26 Financial Performance Overview

    KNR Constructions reported a consolidated revenue of INR 646 crores for Q2 FY26, with an EBITDA of INR 192 crores, translating to a margin of 29.8%. The net profit for the quarter stood at INR 105 crores. For the first half of FY26, consolidated revenue was INR 1,259 crores, with an EBITDA of INR 375 crores (29.8% margin) and a net profit of INR 228 crores. Standalone performance for Q2 FY26 saw revenue at INR 493 crores and a lower EBITDA margin of 10.9%, impacted by a one-off📎 variable pay of INR 10 crores to directors and expenditures for the Kerala project.

    02

    Order Book and Inflow Outlook

    As of September 30, 2025, the company's total order book was INR 8,748 crores, with 29% from road projects, 18% from irrigation, 12% from pipeline, and 41% from mining. Management aims for an order inflow of INR 8,000-10,000 crores by the end of FY26, comprising NHAI, irrigation, and state government projects. However, they acknowledged a 'worst time ever faced' for order inflows due to NHAI's silence period and PMO sanction issues, expecting revenues to be 'down coming 3 to 4 quarters.'

    03

    HAM Project Progress and Challenges

    The company's HAM projects are nearing completion, with Ramanattukara to Valanchery at 99% and Valanchery to Kappirikkad at 98% physical progress as of September 30, 2025. KNR Ramanattukara Infra Private Limited received a provisional completion certificate on July 18, 2025, after agreeing to construct a viaduct at its own cost by February 20, 2026. The Kushalnagara Package 5 HAM project faces delays due to local demands for service roads, with land acquisition stalled at 85-88% for an 8-8.5 km stretch.

    04

    Irrigation Project Receivables and Execution

    KNR Constructions has significant outstanding irrigation receivables, totaling around INR 758 crores out of INR 1,090 crores in total debtors. Specifically, INR 670 crores for the Kaleshwaram Package 4 project are certified but unpaid. Management is in discussions with government officials and expects payment release, with some payments for Package 3 already received post-September 2025. Most irrigation work is expected to be completed this year, with some spillover into next year for Package 3.

    05

    Mining Project Development

    The mining project, valued at INR 3,500 crores, is in a 12-month development phase, primarily focused on land acquisition and clearances. The company expects to execute approximately INR 90 crores of work in the next year during this development period. Upon commencement of operations, the initial revenue is projected to be around INR 300-400 crores, eventually scaling up to INR 3,500 crores over a five-year operation period.

    06

    Sector Outlook and NHAI Initiatives

    The industry experienced sluggishness in project awarding and execution in H1 FY26 due to monsoon and NHAI delays. However, management anticipates a clear pickup in H2 FY26, supported by government focus on infrastructure, including 25 new greenfield expressways and INR 1 trillion investment in religious tourism road links. NHAI's tightening of RFP provisions to favor contractors with proven technical and financial strength is seen as an encouraging development. The full-year NHAI awarding target is around 3,000 kilometers.

    07

    Capital Allocation and Debt Position

    The company has invested INR 698 crores out of the INR 991 crores revised equity requirement for its 8 HAM projects, with an additional INR 292 crores to be infused in FY26 and FY27. Consolidated debt increased to INR 2,338 crores as of September 30, 2025, from INR 1,865 crores in March 2025, resulting in a net debt to equity ratio of 0.49x (up from 0.41x). Capex for the first six months was only INR 3 crores, with an additional INR 30-40 crores planned for the balance of FY26. The company is also in advanced stages of monetizing four assets, with a deal expected to close by month-end.

    This is an AI-generated summary of a publicly available earnings call transcript. It is for informational purposes only and does not constitute investment advice, a recommendation, or an endorsement. inve.money is not a SEBI-registered investment advisor. Please consult a qualified financial advisor before making any investment decisions.