Skip to content

    SJVN Limited

    SJVN
    Power·30 May 2025
    Management Summary

    SJVN reported a strong Q4 FY25 with a 25.44% YoY increase in total generation for FY25, driven by improved performance from its hydro assets. The company made significant strides in capacity expansion, commissioning 320 MW of solar power and signing PPAs for 5.188 GW. However, the quarter saw an impairment loss of INR 143 crores and a decline in other income due to capital deployment. SJVN outlined ambitious capex plans for the coming years and provided detailed timelines for its under-construction projects.

    Highlights

    9
    • Total generation for FY25 reached 10,647 million units, a 25.44% increase year-over-year from 8,489 million units in FY24.

    • Nathpa Jhakri Hydro Power Station (1500 MW) achieved 7,421.45 million units generation, up from 6,311.80 million units in FY24.

    • Rampur Hydroelectric Power Station (400 MW) generated 2,074 million units, an increase from 1,778 million units in the previous year.

    • Commercial operation of 320 MW Bikaner Solar Power project achieved, with the remaining 680 MW of the 1000 MW capacity to be commissioned by October 2025.

    • Foundation stone laid for 100 MW Nava Solar Power project in Rajasthan, expected to generate 254 million units annually at a tariff of 2.62 per unit.

    • PPAs signed for 5.188 GW of capacity, including 210 MW Luhri HEP, 115 MW Sunni Dam, and 200 MW Arun 3 HEP, with 3 GW signed in FY25.

    • Buxar Thermal Plant Unit 1 (660 MW) is expected to achieve commercial operation by July 15, 2025, generating 9,828 million units per annum.

    • Received prestigious CBIP award for Nathpa Jhakri as the best maintained project in the hydro sector.

    • Q4 FY25 incentive income was INR 115 crores, comprising INR 35 crores from capacity incentive, INR 76 crores from secondary energy, and INR 4 crores from UI charges.

    Concerns

    3
    • Reported an impairment loss of INR 143 crores in Q4 FY25, primarily due to the cyclicality of the solar business and actual energy generation dipping below design energy.

    • Other income declined by nearly 50% in Q4 FY25, attributed to capital deployment into under-construction projects, reducing funds held in FDs.

    • Ongoing court case with the Himachal Pradesh government regarding some projects, though construction continues with an expectation of reimbursement with interest if projects are taken over.

    What Changed2

    vs Q2 FY26

    Guidance items10 → 11 (+1)Risks discussed4 → 3 (-1)

    Key financials

    Single quarter

    05 metrics
    1. 01Total Generation10,647 Mn+25.4%YoY
    2. 02Nathpa Jhakri Generation7,421.45 Mn+17.6%YoY
    3. 03Rampur HEP Generation2,074 Mn+16.7%YoY
    4. 04Impairment Loss₹143 Cr
    5. 05Incentive Income₹115 Cr

    Order Book

    high confidence

    Total Value

    5.188 gigawatt

    as of 2025-03-31

    quantified

    Inflow this qtr

    3 gigawatt

    Composition

    Mix3 project types
    • Luhri Hydroelectric Project210 megawatt40.0%
    • Sunni Dam115 megawatt21.9%
    • Arun 3 HEP200 megawatt38.1%

    Share of order book by project type (derived from disclosed amounts)

    Pipeline

    other

    Tenders floated for 18.6 GW, LOAs issued for 13.748 GW, under construction portfolio of 4601 MW

    "SJVN has a robust pipeline and has secured 100% PPAs for its renewable projects, ensuring revenue visibility."

    Source:
    Prepared remarks

    Capital allocation

    2
    high confidence
    CategoryHeadline
    Capex

    ₹8,300 crores

    Debt

    Debt disclosed

    Guidance & targets

    11
    CategoryTargetPriority
    Capacity
    Capacity Addition FY25
    190 MW
    High
    Capacity
    Capacity Addition FY26
    4995 MW
    High
    Capacity
    Buxar Thermal Plant Unit 1 COD
    July 15, 2025
    High
    Capacity
    Bikaner Solar Power Project Completion
    October 2025
    High
    Capacity
    Solar Commissioning by Sep 2025
    680 MW
    High
    Capacity
    Total Solar + Thermal Commissioning by Dec 2025
    ~2500 MW
    Medium
    Capex
    Capex FY25
    INR 7,800 crores
    High
    Capex
    Capex FY26
    INR 8,300 crores
    High
    Capex
    Capex FY27
    INR 12,000 crores
    High
    Profitability
    REIA Trading Margin
    INR 200 crores
    Medium
    Regulated Equity
    Regulated Equity FY26/FY27
    INR 1,945 crores
    High

    Buxar Thermal Plant Unit 1 Commercial Operation Date (COD)

    next quarter
    CurrentSteam blowing completed, heading towards synchronization
    TargetCommercial operation by July 15, 2025

    Why it matters

    This 660 MW thermal unit is a significant capacity addition expected to generate 9,828 MU annually, impacting future revenue and profitability.

    steam blowing for the Unit 1 of our Buxar Thermal Plant 660 megawatt first unit was completed in January '25 and now we are heading towards the synchronization of the machine and also the commercial operation date which we will be achieving by 15th of July during this 2025.

    How to verify

    guidance_and_targets[metric='Buxar Thermal Plant Unit 1 COD']

    Risks & concerns

    3
    RiskSeverity

    Court case with Himachal Pradesh government

    Ongoing legal dispute regarding some projects, but construction continues with expectation of reimbursement with interest if projects are taken over by the state.Analyst acknowledged

    medium

    Impairment loss on projects

    INR 143 crores impairment loss in Q4 FY25, primarily due to cyclicality in solar business and actual generation being lower than design energy; noted as an accounting compulsion that can be reversed.Management acknowledged

    medium

    Project delays due to clearances (Arunachal Pradesh)

    Hydro projects in Arunachal Pradesh require multiple clearances (FC1, EC, land acquisition, investment approval) which are in process, with management expediting them for construction start by year-end.Management acknowledged

    medium

    Q&A highlights

    8

    “Yes, I just want to convey you that yes there is some cases going on with government of HP, but that is not impacting our construction of the projects because unless some decision is taken to handover or takeover of these projects or discontinuation of the projects or whatever we have spent on the projects that is given to us. So we have not anything not decided as of now. So the construction is going on all the three projects which are under dispute. ... No, that they will be definitely reimbursing it to us. That is the understanding and accordingly the same has been conveyed to government of HP by the central government. ... Mr. Mohit, they will be reimbursing all the costs which we have already incurred and which we are going to incur till the final decision is taken. The reimbursement will be along with interest.”

    Addresses the regulatory risk and potential financial impact of ongoing legal disputes with the state government, clarifying that construction continues and costs will be reimbursed with interest.

    asked by Mohit Surana

    2 min read5 chapters

    Detailed Narrative

    01

    Strong Generation Performance and Capacity Additions

    SJVN demonstrated robust operational performance in FY25, with total generation increasing by 25.44% year-over-year to 10,647 million units. This growth was primarily driven by its flagship Nathpa Jhakri Hydro Power Station, which generated 7,421.45 million units, an 17.57% increase from the previous year. The company also made significant progress in capacity expansion, commissioning 320 MW of the 1000 MW Bikaner Solar Power project, with the remaining 680 MW targeted for commissioning by October 2025. Additionally, the foundation stone was laid for the 100 MW Nava Solar Power project, expected to generate 254 million units annually.

    02

    Strategic Project Pipeline and PPA Securitization

    SJVN has a substantial under-construction project portfolio totaling 4601 MW, comprising 4 hydro, 1 thermal, and 11 solar projects. The company has successfully secured Power Purchase Agreements (PPAs) for 5.188 GW of capacity, with 3 GW of these PPAs signed in FY25 alone. Management confirmed that 100% of its renewable projects have secured PPAs through competitive bidding, ensuring revenue visibility. For hydro projects, PPAs are based on a cost-plus model, indicating a secure off-take strategy for its expanding capacity.

    03

    Capital Expenditure and Debt Strategy

    The company reported a capex of approximately INR 7,800 crores for FY25. Looking ahead, SJVN has ambitious capex targets of INR 8,300 crores for FY26 and INR 12,000 crores for FY27, primarily directed towards its under-construction hydro, thermal, and solar projects. While most of the debt for current projects is already tied up, the company anticipates potentially raising an additional INR 2,000 crores in FY26 if required to fund ongoing project development.

    04

    Regulatory and Financial Adjustments

    SJVN recorded an impairment loss of INR 143 crores in Q4 FY25, which management attributed to the cyclical nature of the solar business and actual energy generation falling below design expectations. This was noted as an accounting compulsion with potential for reversal in the future. The company also experienced a nearly 50% decline in other income during Q4 FY25, a consequence of deploying capital from fixed deposits into its extensive pipeline of under-construction projects. An ongoing court case with the Himachal Pradesh government regarding certain projects was acknowledged, with management asserting that construction continues and costs would be reimbursed with interest if the state takes over the projects.

    05

    Arunachal Pradesh Hydro Project Development

    Significant progress is being made on the Italian hydroelectric project in Arunachal Pradesh. The company expects to receive FC1 forest clearance next month, followed by environment clearance by August/September. Land acquisition is anticipated to be completed by the end of June, with investment approval from the Cabinet Committee by September/October. These milestones are critical for the project, with construction expected to commence by the end of the year, contributing to SJVN's long-term hydro capacity.

    This is an AI-generated summary of a publicly available earnings call transcript. It is for informational purposes only and does not constitute investment advice, a recommendation, or an endorsement. inve.money is not a SEBI-registered investment advisor. Please consult a qualified financial advisor before making any investment decisions.