Skip to content

    SJVN Limited

    SJVN
    Power·10 Nov 2025
    Management Summary

    SJVN Limited reported significant operational progress in Q2 FY26, with key projects like Buxar Thermal Unit 1 nearing COD and substantial renewable capacity additions underway. Despite a 6.3% increase in H1 generation, revenue growth was muted due to operational challenges from natural calamities and increased costs. The company maintains an aggressive capex plan for FY26 and FY27, but faces hurdles in PPA finalization and grid connectivity for its large renewable pipeline, alongside managing a growing debt profile.

    Highlights

    5
    • Unit 1 of 60 MW Buxar Thermal Power Project virtually inaugurated on August 22, 2025, with COD expected within 1-2 days of the call.

    • Commercial operation date for cumulative capacity of 680 MW under the 1,000 MW Bikaner solar project has been achieved in phases.

    • Total generation for H1 FY26 increased by 6.3% to 9,442 million units compared to the previous year.

    • Power Purchase Agreements (PPAs) signed for 1,490 MW from Arun-III, Luhri Stage-I, and Sunni Dam Hydroelectric Projects.

    • FY26 capex target of INR 7,500 crores, with INR 3,600 crores already spent in H1, indicating strong execution.

    Concerns

    3
    • Revenue for Q2 FY26 was comparable to Q2 FY25 despite new capacity additions, attributed to lower plant availability factor (due to floods/silt), increased tax expenses (80 IEA benefit expiry), and higher finance/depreciation costs.

    • Grid connectivity and transmission line shortages are delaying commissioning of new Renewable Energy (RE) projects and PPA signing for awarded LOAs (13.74 GW LOAs issued, but only 3.74 GW PPAs signed).

    • Total debt is approximately INR 30,000 crores, raising analyst questions about debt-to-equity ratio and servicing capacity.

    What Changed2

    vs Q4 FY26

    Guidance items11 → 10 (-1)Risks discussed5 → 4 (-1)
    Key financials

    Metrics

    8

    Periods

    5

    Headline

    4
    • Incentive Income
      ₹104.45 Cr
    • Finance Cost Increase (YoY)
      ₹50 Cr
    • Lower Bank Interest Income (YoY)
      ₹26 Cr
    • Decrease in Late Payment Surcharge (YoY)
      ₹17 Cr

    Q2 FY25

    1
    • Depreciation
      ₹133 Cr

    Q2 FY26

    1
    • Depreciation
      ₹171 Cr
      YoY+28.6%

    H1 FY25

    1
    • Total Generation
      880 Mn

    H1 FY26

    1
    • Total Generation
      9,442 Mn
      YoY+6.3%

    Order Book

    high confidence

    Total Value

    5,091 megawatt

    as of 2025-09-30

    quantified

    Composition

    Mix3 technologys
    • Hydro Projects30.6%
    • Thermal Project25.9%
    • Solar Projects43.5%

    Share of order book by technology

    Pipeline

    L1 awaiting loa

    LOAs issued for capacity

    "The company has a significant under-construction portfolio and a large pipeline of awarded LOAs, but faces challenges in converting LOAs to PPAs due to grid connectivity and transmission issues."

    Source:
    Prepared remarks

    Capital allocation

    2
    high confidence
    CategoryHeadline
    Capex

    ₹7,500 crores

    Debt

    Gross ₹30,000 crores

    Guidance & targets

    10
    CategoryTargetPriority
    Capacity
    Buxar Thermal Power Project Unit 1 (660 MW) COD
    Commercial operation
    High
    Capacity
    Buxar Thermal Power Project Unit 2 (660 MW) COD
    Commercial operation
    High
    Capacity
    Bikaner Solar Power Project (320 MW) commissioning
    Commissioned
    High
    Capacity
    Total Solar capacity commissioning
    ~650 MW
    High
    Capacity
    Dhaulasidh Hydro Project (66 MW) commissioning
    Commissioned
    High
    Generation
    Buxar Thermal Power Project annual generation
    9826.72 million units
    High
    PPA Signing
    PSA/PPA for awarded LOAs
    ~3.75 GW
    Medium
    Capex
    FY26 Capex
    INR 7,500 crores
    High
    Capex
    FY27 Capex
    INR 8,000 crores
    High
    Capex
    FY28 Capex
    Similar range as FY27
    Medium

    What to watch in Q3 FY26

    5

    Buxar Thermal Power Project Unit 1 COD declaration

    Next quarter (within 1-2 days of Nov 10, 2025)
    CurrentFull load operation completed, declaration pending
    TargetCommercial Operation Date declared

    Why it matters

    Marks the start of revenue generation from a major thermal project, crucial for financial performance.

    we will be I think declaring within may be today itself may be in the evening itself or may be tomorrow max we will be declaring the commercial operation date for the unit 1

    Risks & concerns

    4
    RiskSeverity

    Declining Plant Availability Factor (PAF) due to natural calamities

    Floods and high silt in the Himalayas affected Rampur and Nathpa Jhakri plants, leading to shutdowns and an estimated revenue loss of INR 50-60 crores.Management acknowledged

    medium

    Grid connectivity and transmission line shortages

    A major issue delaying commissioning of new RE projects in Rajasthan and Gujarat, with connectivity delays of 28-31 months, impacting project timelines.Management acknowledged

    high

    Delays in PPA signing for awarded LOAs

    Out of 13.74 GW of LOAs issued, only 3.74 GW of PPAs have been signed, with clarity on the remaining ~9 GW expected in 1-2 months, potentially leading to re-bidding.Management acknowledged

    high

    Increasing debt levels

    Total debt stands at approximately INR 30,000 crores, but management is confident in servicing it with cash flows from new projects like Buxar.Analyst acknowledged

    medium

    Q&A highlights

    8

    “Incentive income for the half year, current half year it is INR104.45 crores.”

    Provides a specific financial metric for the half-year, indicating a component of non-operating income.

    asked by Ragini

    3 min read5 chapters

    Detailed Narrative

    01

    Q2 FY26 Operational Highlights and Commissioning Progress

    SJVN Limited reported significant operational milestones in Q2 FY26. Unit 1 of the 60 MW Buxar Thermal Power Project was virtually inaugurated on August 22, 2025, and is expected to declare Commercial Operation Date (COD) within 1-2 days of the call. The cumulative 680 MW capacity under the 1,000 MW Bikaner solar project has also achieved COD in phases. The company's total operational capacity now stands at 3,146 MW, with an additional 320 MW from Bikaner expected to be commissioned by December 2025.

    02

    Generation Performance and Revenue Headwinds

    For the first half of FY26, total generation from all power stations reached 9,442 million units, reflecting an improvement of about 562 million units or 6.3% compared to the corresponding period of 2024-2025 (which was stated as 880 million units, likely a typo for 8,880 million units). Despite this growth and capacity additions, Q2 FY26 revenue was comparable to Q2 FY25. This was primarily due to a decrease in energy charges from a lower plant availability factor, resulting in an estimated loss of INR 50-60 crores, caused by floods and high silt affecting hydro plants like Rampur and Nathpa Jhakri. Additionally, increased tax expenses (due to 80 IEA benefit expiry) and higher finance costs (up ~INR 50 crores) impacted profitability.

    03

    Capex and Debt Management

    SJVN has outlined an aggressive capital expenditure plan, with INR 3,600 crores already spent in the first two quarters of FY26 against a full-year target of INR 7,500 crores. The company projects a capex of INR 8,000 crores for FY27, with a similar range expected for FY28. The total debt currently stands at approximately INR 30,000 crores. Management expressed confidence in servicing this debt, anticipating that cash generated from the newly commissioned Buxar project will contribute significantly to debt repayment over the next two years.

    04

    Renewable Energy Pipeline and PPA Challenges

    The company has floated tenders for 19.8 GW of renewable capacity and issued Letters of Award (LOAs) for 13.74 GW. Power Purchase Agreements (PPAs) have been executed for 3.74 GW, with an additional 3.75 GW expected to be signed in the next two months. However, a significant challenge remains with approximately 9 GW of LOAs for which PPAs are yet to be signed. This delay is attributed to issues with grid connectivity and transmission line shortages, particularly affecting projects in Rajasthan and Gujarat. Management is engaged in stakeholder consultations, with clarity on the path forward for these unsigned PPAs expected within 1-2 months.

    05

    Future Capacity Expansion and Project Development

    SJVN's total under-construction portfolio stands at 5,091 MW, comprising 1,558 MW hydro, 1,320 MW thermal, and 2,213 MW solar projects. Beyond the imminent Buxar and Bikaner commissionings, the company plans to commission approximately 650 MW of solar capacity in FY26, including projects in Jamui (75 MW), Assam (120 MW), Bagodara (35 MW), and Nawa (100 MW). Major hydro projects like Etalin (3,097 MW) and Attunli (688 MW) in Arunachal Pradesh are progressing, with Etalin in the final stages of land acquisition. Additionally, the Dhaulasidh Hydro Project (66 MW) is targeted for commissioning by December 2026.

    This is an AI-generated summary of a publicly available earnings call transcript. It is for informational purposes only and does not constitute investment advice, a recommendation, or an endorsement. inve.money is not a SEBI-registered investment advisor. Please consult a qualified financial advisor before making any investment decisions.