Skip to content

    SJVN

    SJVN
    Power·15 May 2026
    Management Summary

    SJVN reported a strong operational and financial performance in FY26, with significant growth in generation and revenue, driven by new capacity additions and tariff adjustments. However, profitability was impacted by initial losses in newly commissioned thermal and solar projects due to lower plant load factors and project delays. The company is actively pursuing its renewable energy pipeline but faces challenges in PPA execution and grid integration for some projects.

    Highlights

    5
    • Total generation from all power stations increased by 25% YoY to 13,302 million units in FY26, reflecting strong operational performance.

    • Revenue from operations for FY26 increased by 22% YoY to INR 3,545 crores, primarily driven by tariff true-up for Nathpa Jhakri and Rampur Hydro Power Stations.

    • PAT for FY26 grew 4% YoY to INR 1,008 crores, with Q4 FY26 PAT surging 303% YoY to INR 125 crores.

    • Commissioned 1,730 MW of new capacity in FY26, including 1,070 MW solar and 660 MW thermal, bringing total installed capacity to 4,196 MW.

    • Awarded 16 GW of renewable energy projects and signed PPAs for approximately 6 GW of capacity.

    Concerns

    5
    • SGEL (solar subsidiary) reported a loss of INR 258 crores in FY26, up from INR 151 crores in FY25, due to lower CUF and finance/depreciation costs.

    • Buxar Thermal Power Plant (STPL) incurred a loss of INR 93 crores in its first three months of operation (Q4 FY26) due to running at a 60% PLF, below the 70% required for profitability.

    • Curtailment of 120 MW in the 1,000 MW Bikaner solar project due to delays in commissioning the required SVR (Static Var Compensator) until October 2026.

    • Nepal hydro project commissioning delayed to December 2028 due to geological issues with the dam and uncertainties in the Nepal government side.

    • Challenges in signing PPAs for the remaining 9 GW of awarded renewable capacity, attributed to DISCOM demand configurations and tariff changes.

    Key financials

    Metrics

    8

    Periods

    3

    Headline

    1
    • Trade Receivables (Mar 31, 2026)
      ₹1,299 Cr
      YoY+4.0%

    Q4 FY26

    2
    • Revenue from Operations
      ₹2,934 Cr
      YoY+5.6%
    • PAT
      ₹125 Cr
      YoY+3.0%

    FY26

    5
    • Revenue from Operations
      ₹3,545 Cr
      YoY+22%
    • Other Income
      ₹325 Cr
      YoY-8.4%
    • Finance Cost
      ₹910 Cr
      YoY+25.3%
    • Depreciation & Amortization
      ₹632 Cr
      YoY+40.4%
    • PAT
      ₹1,008 Cr
      YoY+3.9%

    Order Book

    high confidence

    Total Value

    6 Gigawatt

    as of 2026-03-31

    quantified

    Composition

    Mix2 others
    • Pure Solar41.7%
    • Solar plus BESS15.0%

    Share of order book by other · partial disclosure (56.7% of book)

    Pipeline

    deal pipeline tcv

    Balance 9 Gigawatt of awarded capacity for which PPAs are pending or under progress.

    "Management acknowledges challenges in signing PPAs for the remaining awarded capacity due to DISCOM demand configurations and tariff changes, but remains hopeful for conversion."

    Source:
    Prepared remarks

    Capital allocation

    2
    high confidence
    CategoryHeadline
    Capex

    ₹9,400 crores

    Dividend

    ₹0.35/share (final)

    Guidance & targets

    11
    CategoryTargetPriority
    Capacity
    Buxar Thermal Power Plant Unit 2 commissioning
    End of May 2026
    High
    Capacity
    Dhaulasidh Hydro Electric Project commissioning
    March 2027
    High
    Capacity
    Solar capacity commissioning
    1,555 Megawatt
    High
    Capacity
    Solar capacity commissioning
    650 Megawatt
    High
    Capacity
    Nepal hydro project commissioning
    December 2028
    High
    Capacity
    SVR commissioning for Bikaner solar
    October 2026
    High
    Capacity
    Long-term capacity target
    Under review
    Medium
    Profitability
    Buxar Thermal Power Plant profitability
    Profitable
    High
    Capex
    Capex plan
    9,400 crores
    High
    Capex
    Capex plan
    7,800 crores
    High
    Capex
    Capex plan
    7,500 crores
    High

    Buxar Thermal Power Plant Unit 2 commissioning

    next quarter
    CurrentExpected by end of May 2026
    TargetCommercial operation achieved

    Why it matters

    Successful commissioning of Unit 2 is crucial for full capacity utilization and improved profitability of the Buxar plant.

    I am also pleased to inform that unit 2 of the project is successfully synchronized with the national grid on 8th of May 2026 and its commercial operation is expected to be achieved by the end of this month.

    How to verify

    guidance_and_targets[metric='Buxar Thermal Power Plant Unit 2 commissioning']

    Risks & concerns

    5
    RiskSeverity

    Initial losses in new thermal and solar projects

    SGEL and Buxar Thermal Power Plant incurred losses in FY26 due to lower PLF (Buxar at 60%) and higher finance/depreciation costs, impacting overall profitability.Management acknowledged

    medium

    Project delays and cost overruns for Nepal hydro project

    The Nepal hydro project's commissioning is delayed to December 2028 due to geological surprises at the dam site and uncertainties in the Nepal government, requiring additional stabilization time.Management acknowledged

    medium

    Curtailment of solar power generation due to grid infrastructure

    The 1,000 MW Bikaner solar project is experiencing 120 MW curtailment due to delays in commissioning the Static Var Compensator (SVR), expected by October 2026. Potential curtailment also exists for Khawada projects due to transmission line delays.Management acknowledged

    medium

    Challenges in PPA execution for awarded renewable capacity

    Out of 15 GW awarded renewable capacity, PPAs for 9 GW are still pending due to DISCOMs' varying demand configurations, tariff changes, and simultaneous tenders, posing a risk to project realization.Management acknowledged

    medium

    Revision of long-term capacity targets

    The ambitious long-term targets of 25 GW by 2030 and 50 GW by 2040 are under review due to past project delays and lower CUF in commissioned projects, indicating a potential downward revision.Management acknowledged

    low

    Q&A highlights

    8

    “The losses were in SGEL we had a loss of around INR 257 crores and in Buxar Thermal i.e. STPL, we had a loss of around INR 92 crores. Buxar, as you know, has been operational for around three months in the last year and it has started operating at a PLF of around 60%.”

    Analyst questioned the consolidated losses, and management clarified the specific losses from SGEL and STPL, attributing them to initial operational challenges and lower PLF.

    asked by Mohit Kumar

    2 min read5 chapters

    Detailed Narrative

    01

    Strong Operational and Financial Performance in FY26

    SJVN demonstrated robust operational performance in FY26, with total power generation increasing by approximately 25% YoY to 13,302 million units. This growth was supported by flagship projects like Nathpa Jhakri Hydro Power Station, which generated 7,506 million units, and Rampur Hydro Power Station, which generated 2,108 million units. Financially, the company reported a 22% YoY increase in revenue from operations to INR 3,545 crores for FY26, primarily due to the recognition of INR 679 crores from tariff true-up for prior periods. PAT for FY26 grew 4% YoY to INR 1,008 crores, with a significant 303% YoY surge in Q4 FY26 PAT to INR 125 crores.

    02

    Significant Capacity Additions and Project Progress

    In FY26, SJVN added 1,730 MW to its operating assets, comprising 1,070 MW of solar and 660 MW of thermal capacity, bringing the total installed capacity to 4,196 MW. Key additions include the 660 MW first unit of the Buxar Thermal Power Plant and a 1,000 MW Bikaner solar project. The second unit of Buxar (660 MW) is expected to achieve commercial operation by the end of May 2026. Progress is also noted for the 69.5 MW Dhaulasidh Hydro Project, targeted for commissioning by March 2027, and the Arun-III hydro project in Nepal, now expected by December 2028 despite earlier geological and governmental challenges.

    03

    Renewable Energy Portfolio Expansion and PPA Challenges

    SJVN continues to expand its renewable energy footprint, having awarded 16 GW of renewable energy projects across various segments. The company has signed Power Sale Agreements (PSAs) for approximately 6 GW of this awarded capacity. However, challenges persist in converting the remaining 9 GW into signed PPAs, largely due to varying demand configurations from DISCOMs and evolving tariff structures. Management expressed hope for converting these pending PPAs, noting that some tariffs are attractive compared to current market rates.

    04

    Initial Profitability Challenges in New Projects

    Newly commissioned projects, particularly in the solar (SGEL) and thermal (STPL - Buxar) segments, faced initial profitability challenges. SGEL reported a loss of INR 258 crores in FY26, while Buxar Thermal Power Plant incurred a loss of INR 93 crores in its first three months of operation. These losses are attributed to lower Plant Load Factors (PLF), with Buxar operating at 60% against a required 70% for profitability, and higher finance and depreciation costs. Management anticipates Buxar to become profitable in FY27 as Unit 2 commissions and Unit 1 stabilizes.

    05

    Capital Expenditure Plans and Long-Term Target Review

    SJVN has outlined substantial capital expenditure plans for the coming years, with INR 9,400 crores projected for FY27, INR 7,800 crores for FY28, and INR 7,500 crores for FY29. The company's ambitious long-term capacity targets of 25 GW by 2030 and 50 GW by 2040 are currently under review. This reassessment is prompted by past project delays, lower-than-expected CUF in some commissioned projects, and challenges in the broader tendering environment, indicating a potential recalibration of future growth projections.

    This is an AI-generated summary of a publicly available earnings call transcript. It is for informational purposes only and does not constitute investment advice, a recommendation, or an endorsement. inve.money is not a SEBI-registered investment advisor. Please consult a qualified financial advisor before making any investment decisions.