Inve US ▾
AEAEM

Agnico Eagle (AEM) Q1 FY26 earnings call: guidance and Q&A

Earnings call· Mar 2026 (Q1 FY26)· Materials· May 1, 2026

Source: earnings call transcript

Executive summary

Agnico Eagle Q1 FY26 — Record earnings on strong operations and exceptional gold prices

Agnico delivered a record financial quarter on solid operations and exceptional gold prices, with production modestly ahead of budget while both cash cost and AISC guidance were reiterated in a volatile input environment. The balance sheet strengthened materially — net cash near $2.9B and a Fitch upgrade — even after absorbing ~$1.8B of cash taxes, leaving room to reinvest, return ~40% of FCF and lift the buyback authorization to $2B. The forward story is growth-pipeline execution: five value-driver projects (30–60% IRR) underpinning 20–30% production growth over the next decade, with Detour and Malartic each targeted at 1M oz, Hope Bay heading toward a May construction decision, and a newly consolidated Finnish land package framed as a future 500,000 oz/yr platform. Management paired the record quarter with an unusually direct acknowledgement of two fatalities and a company-wide safety stand-down.

Highlights

5
  • Record adjusted net income of ~$1.7B ($3.41/share, non-GAAP) and adjusted EBITDA just over $3B, with record operating margins

  • Gold production of ~825,000 oz, slightly above budget and ~24% of the annual guidance midpoint; total cash costs $1,093/oz and AISC $1,483/oz both tracking within full-year guidance

  • ~$730M free cash flow generated despite paying ~$1.8B of 2026 cash taxes in the quarter (including a $1.3B 2025 tax catch-up); net cash rose to ~$2.9B and Fitch upgraded the issuer rating to A-

  • Returned ~$375M to shareholders (~half of FCF) and is raising the NCIB authorization to $2B; 43+ consecutive years of dividends

  • Operating records set at Detour (pit tonnage/mill throughput), Macassa (mill throughput) and Meliadine (development), plus strong exploration and a ~2,500 sq km Finland land consolidation targeting a 500,000 oz/yr multi-decade platform

Concerns

4
  • Two fatalities over the past five months, which management called 'not acceptable'; investigations still ongoing

  • Q1 gold production was lower year-over-year on mine sequencing at LaRonde, Macassa and Fosterville, and total mill tonnage was below plan (~24% of annual midpoint, with the year weighted ~48/52 to H2)

  • Costs pressured by higher royalties on the higher gold price, lower volumes and a stronger Canadian dollar vs Q1 2025; buyback pace slowed to $150M (half of Q4) on the large cash-tax outflow

  • Macassa mill tonnage constrained by old paste-plant issues while commissioning the new plant (expected fully operational Q2); Rupert all-stock acquisition creates share dilution to offset; Finnish mining tax changes factored into models

Guidance & targets

CategoryTargetConfidence
Production
Full-year 2026 production guidance reiterated; ~48% H1 / ~52% H2 weighting, Q1 ~24% of midpoint
high materiality
High
Cost — total cash costs
$1,020–$1,120 per ounce (full-year 2026, reiterated)
high materiality
High
Cost — AISC
$1,400–$1,550 per ounce (full-year 2026, reiterated)
high materiality
High
Capital returns
Return ~40% of annual free cash flow via dividends and buybacks (floor for the year)
high materiality
High
Buyback authorization
Renew NCIB in May on substantially the same terms with an increased limit of up to $2 billion
high materiality
High
Capital expenditure
Total capital spending ~$3 billion in 2026 (all in)
high materiality
High
Production growth (long-term)
Increase production by 20%–30% over the next decade via five key pipeline projects
high materiality
Medium
Project capacity target
Detour complex to 1 million ounces per year
high materiality
Medium
Project capacity target
Malartic (Canadian Malartic) to 1 million ounces per year
high materiality
Medium
Project capacity target
Hope Bay to be over 400,000 oz/yr; potential construction decision in May with the Board
high materiality
Medium
Platform capacity target
Nunavut platform to potentially 1 million ounces per year (with Hope Bay)
medium materiality
Medium
Platform capacity target
Finland platform of 500,000 ounces per year (Kittila + Ikkari/'Icare'), multi-decade
high materiality
Medium
Operational ramp
Macassa mill to over 2,000 tonnes per day by end of year
medium materiality
Medium
Balance sheet target
Maintain net cash position of roughly $3 billion to $5 billion
medium materiality
Medium
Cost assumption
2026 cost guidance assumes average diesel price of $0.78 per liter
low materiality
Medium
Project milestone
Malartic: bring East Gouldie ore to surface via the shaft by mid-2027
medium materiality
Medium
Project milestone
Detour Underground: initiate mining in a targeted area as early as 2028
medium materiality
Low
Guidance timing
September 2026 update on Canadian Malartic (reserves/resources; second shaft, Marban, Wasamac integration and cost/operating ranges)
medium materiality
Medium
Near-term production cadence
Q2 production expected similar to Q1
medium materiality
Medium

Segment performance

SegmentRevenueYoYQoQMargin
Quebec (Canadian Malartic, LaRonde)
Good start led by Malartic; grade benefited from Barnat pit sequencing. Malartic mine life now seen extending toward ~2060 vs 2042 in the 2023 study; East Gouldie ore targeted to surface via shaft by mid-2027.
Malartic first East Gouldie stope mined via ramp ~1 km undergroundSecond-shaft pilot hole reached 1.8 km depthLaRonde autonomous hauling commissioned (3.2 km to 2.9 km underground)
————
Nunavut (Meliadine, Meadowbank, Amaruq, Hope Bay)
Diesel-generated power in Nunavut is largely hedged/pre-positioned via the short barge season. Hope Bay could take the Nunavut platform toward ~1 Moz/yr.
Record development rates at MeliadineHope Bay engineering over 50% complete; potential May construction decisionHope Bay target: over 400,000 oz/yr
————
Ontario (Detour Lake, Macassa)
Macassa total mill tonnage below plan due to old paste-plant issues while commissioning the new plant (expected fully operational Q2). Detour Underground high-intensity drilling targeting mining as early as 2028; both Detour and Macassa complexes central to Ontario growth.
Detour: quarterly record tonnes mined and record Q1 mill throughput; lowest quarterly turnover since open-pit startDetour Underground ramp: 820 m development, ~147 m depthMacassa: record Q1 mill throughput; ramping toward >2,000 tpd by year-endUpper Beaver ramp >500 m (108 m depth); shaft reached 382 m
————
Australia (Fosterville)
Performed very well on mine-optimization efforts; management encouraged by recent exploration results on consolidated land around Fosterville, though early stage. Fosterville sequencing contributed to lower YoY company production.
Significant step change in productivity in development and stope cycling
————
Mexico (San Nicolas — 50% JV)
Management would consider consolidating the 50% JV if the partner were open; no other substantial Mexican opportunities currently identified.
Awaiting regulatory decision on key permitsEngineering of critical infrastructure advancing; condemnation and geological drilling ongoing
————
Finland (Kittila; pending Rupert/Orion/Fingold)
Consolidation removes prior property-boundary constraints on the Ikkari deposit; revised concept targeted by end of 2027. Nickel/copper/PGE potential in the same rock package noted as possible add-on.
Land consolidation of ~2,500 sq km underwayVision of 500,000 oz/yr multi-decade platform (Kittila + Ikkari)Finnish mining-sector tax change factored into Kittila life-of-mine modeling
————

Orderbook & backlog

Growth-project pipeline (five value-driver projects) 20%–30% production growth over the next decade 2026-03-31

Reframed from sales order book to capital-project backlog per sector guidance. Projects: Detour (to 1 Moz), Malartic (to 1 Moz), Hope Bay (>400 koz/yr), Upper Beaver, San Nicolas; cited at 30–60% IRR.

Finland growth platform (Kittila + Ikkari) ~500,000 oz/yr multi-decade platform 2026-03-31

newly added via ~2,500 sq km consolidation

Current vision combining Kittila and Ikkari; revised concept expected by end of 2027, with upside to be explored.

Deals & partnerships

Rupert Resources acquisition (all outstanding shares) 100% share consideration

Rupert wanted 100% shares (viewing Agnico stock favorably); core of the Finland consolidation and the 500 koz/yr platform vision. Analyst-implied ~$1,268/oz acquisition-plus-capex figure was not confirmed by management.

Orion Resources acquisition (all outstanding shares) cash

Paid in full cash; part of the three combined Finland transactions consolidating ~2,500 sq km.

B2Gold (Fingold JV) acquisition of 70% interest in Fingold JV cash

Paid in full cash; combined with Rupert and Orion to remove property-boundary constraints in Central Lapland.

B2Gold Nunavut collaboration / knowledge-sharing agreement

Collaboration around B2Gold's Goose operation; Agnico shares operating experience while learning from B2Gold's operations—described as routine peer collaboration.

Capital programs

Hope Bay development (Nunavut) awaiting board construction decision (May) slightly over $2B (below $2.5B)
Spent to date: engineering over 50% complete
Funding: cash on hand / free cash flow (implied; strong net-cash balance sheet)
Start: potential construction decision May 2026

Benefit:over 400,000 oz/yr; mill designed at 6,000 tpd upfront

Camp, fab shops, backup power, mill building and water treatment already in place. Capital slightly above $2B driven by design choices (single-stage 6,000 tpd mill, fast-tracking Patch 7, added drilling/infrastructure) rather than inflation; full economics/sensitivities at the May update.

Detour Underground (Ontario) advancing on schedule (early days)
Spent to date: exploration ramp at 820 m development, ~147 m depth; conveyor-portal overburden excavation begun; camp extension progressed
Start: exploration ramp underway

Benefit:key to Detour complex reaching 1 million oz/yr

High-intensity drill program targeting an area for mining as early as 2028; study team evaluating higher milling capacity, larger underground, and a possible additional pit pushback.

Upper Beaver (Ontario) ahead of schedule
Spent to date: ramp advanced >500 m in the quarter (108 m depth); shaft reached 382 m
Start: shaft sinking commenced Q4 2025

High-intensity drill program continued at the 760 level to complement a planned bulk sample.

Canadian Malartic — East Gouldie shaft & underground ahead of schedule / on plan
Spent to date: first East Gouldie stope mined via ramp ~1 km underground; second-shaft pilot hole to 1.8 km
Start: shaft sinking underway

Benefit:path to Malartic 1 million oz/yr; mine life extended toward ~2060

September 2026 update to integrate second shaft, Marban and Wasamac with cost/operating ranges; full studies later in the year.

San Nicolas (Mexico, 50% JV) awaiting key regulatory permits
Spent to date: advancing engineering of critical infrastructure; condemnation and geological drilling

Management open to consolidating the 50% JV if the opportunity arises; would look at expanding the resource.

Company-wide capital program (FY26) underway
Period spend: ~$3B (all in) in 2026
Spent to date: ~$400M invested in growth projects in Q1
Funding: free cash flow
Start: FY26

Benefit:underpins 20–30% production growth over the decade

Up from ~$2.3B in 2025; management will look to accelerate to bring production forward.

Risks & headwinds

Fatalities / safety past 5 months; investigations ongoing

2 fatalities over the past 5 months

Mitigation:Company-wide mandated safety stand-down engaging every employee; major-hazard identification and critical controls; learnings shared internally and with industry peers; CEO accepted ultimate responsibility.

Diesel price volatility FY26

~7% of operating cost base; 10% diesel move ≈ $6/oz on annual total cash costs after hedges; $0.78/liter assumption

Mitigation:Diesel hedging program, pre-positioned Nunavut fuel via short barge season, underground-weighted portfolio, and hydro/nuclear grid power in Ontario/Quebec.

FX (stronger Canadian dollar) Q1 FY26

contributed to higher Q1 costs vs Q1 2025 (not separately quantified)

Mitigation:Regional operating model and local procurement; continue to monitor.

Higher royalty costs on higher gold price Q1 FY26

cited as a driver of higher AISC ($1,483/oz)

Mitigation:Offset by record realized prices; costs remain within guidance.

Lower YoY production / mine sequencing Q1 FY26; year weighted ~48/52 H1/H2

Q1 ~825,000 oz, lower YoY; ~24% of annual midpoint

Mitigation:Sequencing spread across the year; Q1 still slightly above budget; H2-weighted plan reaffirmed.

Macassa paste-plant commissioning Q1 FY26

total mill tonnage below plan this quarter

Mitigation:New paste plant expected fully operational in Q2; mill ramping toward >2,000 tpd by year-end.

Finnish mining-sector tax change ongoing

not quantified

Mitigation:Factored into Kittila life-of-mine and acquisition evaluations; industry lobbying government to make certain items deductible.

San Nicolas permitting awaiting regulatory decision

not quantified

Mitigation:Advancing engineering and drilling in parallel to derisk execution.

Project inflation / cost overrun (Hope Bay) pre-construction

capital now slightly over $2B (below $2.5B)

Mitigation:Extensive engineering (>50% complete) and in-place infrastructure; increase driven mainly by design choices, not inflation.

Share dilution from Rupert acquisition on close

100% stock consideration for Rupert

Mitigation:Potential additional buybacks funded by portfolio-investment sales to offset dilution.

Q&A highlights

What are the value-creation steps over the next 12–24 months (resource update, study, permitting) to get to the 500,000 oz vision?

Priority is consolidating the property to remove boundary constraints; the team will refreeze scope (mill, tailings, schedule), staff study/construction teams, and drill immediately once the acquisition closes. An updated concept on optimal pit design and infrastructure location is targeted by end of 2027, with iterative updates thereafter.

“by the end of 2027, we should have an idea of the kind of a revised concept based on the current information, while we're going to continue to drill”

asked by Lawson Winder · answered by Guy Gosselin

3 min read 6 chapters

Detailed narrative

Record financial quarter and balance-sheet strength

Agnico reported record adjusted net income of ~$1.7B ($3.41/share, non-GAAP) and adjusted EBITDA just over $3B, with record operating margins driven by solid operations and exceptional gold prices. Free cash flow was ~$730M despite paying ~$1.8B of 2026 cash taxes in the quarter (of which $1.3B was a previously disclosed 2025 tax liability, ~50% of expected 2026 cash taxes).

Net cash rose to ~$2.9B (cash ~$3.1B), described as the strongest balance sheet in company history, and Fitch upgraded the long-term issuer rating to A- with a stable outlook.

Operating performance and cost control

Q1 gold production of ~825,000 oz was slightly above budget and ~24% of the annual guidance midpoint, though lower year-over-year on mine sequencing at LaRonde, Macassa and Fosterville. Total cash costs were $1,093/oz and AISC $1,483/oz, both within reiterated full-year ranges, pressured by higher royalties on the higher gold price, lower volumes and a stronger Canadian dollar.

Management emphasized structural cost advantages: hydro/nuclear grid power in Ontario and Quebec and hedged/pre-positioned diesel in Nunavut, with diesel ~7% of the operating cost base and a 10% diesel move worth only ~$6/oz after hedges.

Growth pipeline execution

Five value-driver projects (cited at 30–60% IRR) are intended to lift production 20–30% over the next decade. Malartic mined its first East Gouldie stope via the ramp ~1 km underground, with the second-shaft pilot hole reaching 1.8 km and ore targeted to reach surface via shaft by mid-2027; the deposit's mine life is now seen extending toward ~2060 versus 2042 in the 2023 study.

Detour set quarterly records in tonnes mined and Q1 mill throughput, with the Detour Underground exploration ramp at 820 m development/147 m depth. Upper Beaver's ramp advanced over 500 m (108 m depth) and its shaft reached 382 m, both ahead of schedule.

Hope Bay is heading toward a potential May construction decision with engineering over 50% complete.

Finland land consolidation

Agnico announced offers to acquire all outstanding shares of Rupert Resources and Orion Resources plus B2Gold's 70% interest in the Fingold JV, consolidating ~2,500 sq km of the Central Lapland greenstone belt. Management frames the combined Kittila + Ikkari base as a potential 500,000 oz/yr multi-decade platform, drawing an analogy to Kittila (acquired 2005 with ~2 Moz, now a ~10 Moz endowment).

A revised concept on optimal pit design and infrastructure location is targeted by end of 2027, with drilling to begin once the acquisition closes and property boundaries are removed.

Continuous improvement and technology

LaRonde commissioned autonomous hauling, moving ore from 3.2 km to 2.9 km underground without drivers—cutting from 4 trucks/8 operators to 2 trucks/1 person and extending effective operating to ~20 hours. Macassa completed an underground LTE network to enable dispatch and short-interval control, and secured approval to process AK deposit ore at the LZ5 facility via LaRonde.

Key continuous-improvement leaders visited Finland to share practices across the company's regions.

Safety

Management opened and closed the call on safety, disclosing two fatalities over the past five months, which the CEO called 'not acceptable' and accepted ultimate responsibility for. The company mandated a company-wide stand-down engaging every employee to reemphasize safety. Investigations remain ongoing with regulatory authorities involved; the company is focusing on major-hazard identification and critical controls, sharing learnings internally and with industry peers.

Summary of the company's earnings call; see how call summaries are prepared. Not investment advice.