Detailed Narrative
Coastal Virginia Offshore Wind (CVOW) Project Status
The CVOW project is 2/3 complete, with 100% of monopile installation successfully finished one month ahead of schedule. 63 transition pieces have been installed, and all 176 are fabricated. The second offshore substation jacket is installed, with the topside to follow, and the third substation will be installed in Q1 2026. First turbine installation is expected late next month, with first power delivery in late Q1 2026. Project completion is still expected by end of 2026, though some final turbines may slip into early 2027 due to Charybdis delays.
Charybdis Vessel Issues
The American-made Jones Act-compliant wind turbine installation vessel, Charybdis, has experienced further delays. While major systems are functional, a punch list of approximately 200 quality assurance items, primarily related to electrical systems and documentation, needs addressing. Crews are working around the clock, having closed out about 120 items. The vessel is expected to be cleared for turbine load-out and installation in November, with any modest delay beyond November not impacting first power timing.
Data Center Demand and Infrastructure
Dominion Energy continues to experience robust data center demand, with 47 GW in various stages of contracting as of September 2025, up 17% from December 2024. This includes 28 GW in substation engineering letters of authorization, 9 GW in executed construction letters of authorization (up 73%), and nearly 10 GW in electric service agreements (up 12%). The company is developing resources across distribution, transmission, and generation to meet this need while safeguarding existing customers from disproportionate costs.
Regulatory and Generation Updates
Post-hearing briefs for the biannual review and proposed large load tariff were filed, with a final order anticipated by end of November. Dominion submitted project proposals in the latest PJM open window process, expecting significant new transmission needs. SCC hearings for the 1 GW Chesterfield Energy Reliability Center concluded, with an order expected in December. The company also filed $2.9 billion of new utility-scale solar (845 MW) and storage (155 MW) projects, and its 2025 Virginia Integrated Resource Plan outlining build portfolios for continued load growth.
Customer Affordability and Nuclear Strategy
Residential electric rates in DEV and DESC are 9% and 11% below the U.S. average, respectively, with bill growth rates projected below electricity inflation. The company's IRP delayed SMR new nuclear by 5 years due to financing and technology considerations, and fit within the overall construction plan. Management emphasized the need for solutions to cost overrun risk and first-of-a-kind costs for new nuclear, potentially through partnerships like the one with Amazon for North Anna 3 SMR financing.