Public Service Enterprise Group delivered solid Q3 FY25 results, narrowing its full-year non-GAAP operating earnings guidance to the upper half of the previous range, driven by new distribution rates. The company reaffirmed its long-term EPS growth outlook and multi-year capital plan, emphasizing its strong balance sheet. Management highlighted the growing supply-demand imbalance in New Jersey, advocating for policy solutions and expressing readiness to work with the incoming administration on energy supply and affordability challenges.

You’re reading a preview. Opening the full call uses 1 concall credit.

Sign in to use your monthly call allowance.

PEG operating KPIs by quarter

PEG operating KPIs stated on its earnings calls, by fiscal quarter
KPIThis call Sep 2025 Q3 FY25 Dec 2025 Q4 FY25 Mar 2026 Q1 FY26 Jun 2026 Q2 FY26Change vs prior quarter
Capital expenditures PSE&G——
~$800M On our regulated capital spending program, PSE&G invested approximately $800 million during the first quarter, and we remain on track to execute our full year 2026 plan, of approximately $4.2 billion, focused on continued investments in infrastructure modernization, energy efficiency, electrification initiatives and load growth. Source: earnings call transcript
~$1B On the capital front, PSE&G invested approximately $1 billion during the second quarter and is on track to execute our full year 2026 regulated capital investment plan, of approximately $4.2 billion, focused on continued investments in infrastructure modernization, energy efficiency, electrification initiatives and load growth. Source: earnings call transcript
—
Nuclear generation PSEG Nuclear—
~7.2 TWh On the operating side, the nuclear fleet produced approximately 7.2 terawatt hours during the fourth quarter of 2025 compared to approximately 7.3 terawatt hours in the fourth quarter of 2024. Source: earnings call transcript
8 TWh That notable accomplishment contributed to a 95.5% capacity factor and supplied 8 terawatt hours of reliable, carbon-free baseload energy to New Jersey and the grid during the first quarter. Source: earnings call transcript
7.8 TWh PSEG nuclear also performed well during the quarter, supplying the grid with 7.8 terawatt hours of carbon-free 24/7 baseload generation and achieving a capacity factor of 92% that included the second consecutive breakthrough breaker run at Salem Unit 2. Source: earnings call transcript
-2.5%
Nuclear generation capacity factor PSEG Nuclear
92.4% Capacity factors for the nuclear fleet were 92.4% and 93.7% for the quarter and 9-month period ended September 30, 2025, respectively. Source: earnings call transcript
83.7% Capacity factors for the nuclear fleet were 83.7% and 91.2% for the quarter and full year of 2025, respectively. Source: earnings call transcript
95.5% That notable accomplishment contributed to a 95.5% capacity factor and supplied 8 terawatt hours of reliable, carbon-free baseload energy to New Jersey and the grid during the first quarter. Source: earnings call transcript
92% PSEG nuclear also performed well during the quarter, supplying the grid with 7.8 terawatt hours of carbon-free 24/7 baseload generation and achieving a capacity factor of 92% that included the second consecutive breakthrough breaker run at Salem Unit 2. Source: earnings call transcript
-3.5 pt