Westwater Resources (WWR) Q2 FY26 earnings call: guidance and Q&A

Earnings call· Jun 2026 (Q2 FY26)· Aug 13, 2026

Source: earnings call transcript

Executive summary

Westwater Resources Q2 FY26 — EXIM Loan Fuels Kellyton Graphite Plant Development

Westwater Resources advanced its Kellyton Graphite Plant development in Q2 FY26, securing a crucial $25 million non-dilutive loan from EXIM, a key step in its broader financing strategy. The company continues to pursue additional government funding while progressing customer qualification and Coosa Graphite Deposit permitting, aiming for commercial production of battery-grade natural graphite in the US. Despite an increased net loss, management remains focused on leveraging its first-mover advantage and integrated supply chain vision.

Highlights

5
  • EXIM approved a $25 million loan for the Kellyton Graphite Plant, a significant non-dilutive financing milestone.

  • Company has invested approximately $130 million in Kellyton Phase 1, establishing a 3- to 5-year first-mover advantage.

  • Kellyton's qualification line has produced over 1 metric ton of CSPG samples for customer evaluation.

  • Coosa Graphite Deposit received covered project designation under the FAST-41 federal permitting program.

  • Secured attractive single-digit cost of capital for the EXIM loan, significantly below private market rates.

Concerns

4
  • Consolidated net loss increased to $4.3 million ($0.03 per share) in Q2 FY26 from $3.9 million ($0.05 per share) in Q2 FY25.

  • Consolidated net loss for H1 FY26 increased to $9 million ($0.07 per share) from $6.5 million ($0.09 per share) in H1 FY25.

  • Remaining Kellyton Phase 1 development capital is $115 million, including $15 million in contingency, still requiring additional financing.

  • Coosa Graphite Deposit permitting is estimated to complete by June 2027, delaying operational readiness until late 2028/early 2029.

Guidance & targets

CategoryTargetConfidence
Kellyton Phase 1 Commercial Production
Could commence as soon as next year
high materiality
Medium
Coosa Graphite Deposit Environmental Review and Permitting Completion
June 2027
medium materiality
High
Coosa Graphite Deposit Operational Readiness
End of 2028, early 2029
medium materiality
Medium
Kellyton Phase 1 Total Development Capital
$245 million
high materiality
High
EXIM Loan Cost of Capital
Single-digit type of cost of capital
medium materiality
High

Deals & partnerships

EXIM Loan approval to support continued development of Kellyton Graphite Plant $25 million Multiyear

Approved under EXIM's Make More in America Initiative. Loan is subject to definitive documentation and customary closing conditions. Structured as a construction loan with draws.

SK On Offtake agreement for anode material

Relationship with customer remains strong. Contract was previously in place.

Stellantis Offtake agreement for anode material

Relationship with customer remains strong. Contract was previously in place.

Capital programs

Kellyton Graphite Plant Phase 1 Development underway $245 million
Spent to date: $130 million
Funding: EXIM loan ($25M), additional government funding and other financing alternatives
Start: Since inception

Benefit:12,500 metric tons per year of CSPG production capacity

Includes approximately $15 million in contingency. Remaining $115 million to be incurred. EXIM loan is for continued development.

Coosa Graphite Deposit Permitting and Development underway

Benefit:Long-term domestic source of natural graphite flake concentrate for Kellyton

Environmental review and permitting estimated to complete by June 2027. Received covered project designation under FAST-41 federal permitting program.

Risks & headwinds

Financing for Kellyton Phase 1 Completion Ongoing

$115 million of $245 million total development capital not yet incurred

Mitigation:Actively pursuing additional government funding sources and other financing alternatives; EXIM loan provides $25 million.

Coosa Graphite Deposit Permitting Timeline Through 2027 and beyond

Environmental review and permitting estimated to complete by June 2027, delaying operational readiness until late 2028/early 2029.

Mitigation:Received covered project designation under FAST-41 federal permitting program to improve timeliness and predictability.

Increased Operating Expenses Q2 FY26, H1 FY26

Consolidated net loss increased to $4.3 million in Q2 FY26 from $3.9 million in Q2 FY25; H1 FY26 net loss increased to $9 million from $6.5 million in H1 FY25.

Mitigation:Partially offset by additional interest income; costs are associated with progressing key projects (Coosa permitting, product development) and strategic initiatives (government funding evaluation).

Low Graphite Flake Prices Current

$500-$600 per ton range, described as historic lows.

Mitigation:Coosa intended to come online in a much higher price environment, with forward curve for flake graphite and anode material still rising.

What to watch in Q3 FY26

EXIM Loan Documentation Finalization

Next quarter
Current Formal approval received
Target Definitive documentation signed and executed

Why it matters

Securing the $25 million non-dilutive capital is critical for continued development of Kellyton Phase 1.

While the loan remains subject to definitive documentation and customary closing conditions, it is an important step towards securing nondilutive capital to support continued development at Kellyton.

Find out whether WWR delivers this. Inve re-checks your case every morning.

Q&A highlights

Are there any components of Kellyton's construction where pricing is not yet set, or is the contingency sufficient to cover potential cost increases within the $245M total?

Management stated that the $245 million forecast includes sufficient contingency (15% for contingency plus escalation) to cover costs, with some items having fixed pricing and others using unit rates. They are comfortable completing the project within budget.

“I'm comfortable with the contingency that we -- and the escalation that we still have in our forecast at completion that we can complete it within the $245 million.”

asked by Heiko Ihle · answered by Frank Bakker

2 min read 6 chapters

Detailed narrative

EXIM Loan Approval and Strategic Importance

Westwater Resources announced a significant milestone with EXIM's approval of a $25 million loan for the Kellyton Graphite Plant. This non-dilutive capital is crucial for advancing Kellyton from construction to commissioning and operational readiness, with commercial production anticipated as soon as next year. The approval underscores the strategic importance of domestic graphite production for the U.S. critical mineral supply chain, aligning with EXIM's Make More in America Initiative.

Kellyton Plant Progress and First-Mover Advantage

The company has invested approximately $130 million in Kellyton Phase 1, which includes existing buildings, equipment on site and on order, an operating qualification line, and an R&D lab. This progress is believed to provide Westwater with a 3- to 5-year first-mover advantage in the domestic battery-grade natural graphite industry. Phase 1 is designed to produce approximately 12,500 metric tons per year of coated spherical purified graphite (CSPG).

Financing Strategy and Future Capital Needs

The EXIM loan is part of a broader financing strategy focused on securing non-dilutive, lower-cost capital. Westwater is actively pursuing additional government funding sources and other alternatives to fund the remaining $115 million of the $245 million total development capital for Kellyton Phase 1. Management emphasized a disciplined and flexible approach to maintain long-term shareholder value.

Coosa Graphite Deposit Permitting

Progress was made on permitting and technical work for the Coosa Graphite Deposit, intended as a long-term domestic feedstock source for Kellyton. Environmental, cultural, hydrologic, and geochemical studies were completed, leading to the submission of a Section 404 permit application to the U.S. Army Corps of Engineers. Coosa received covered project designation under the FAST-41 federal permitting program, with an estimated environmental review and permitting completion date of June 2027, targeting operational readiness by late 2028 or early 2029.

Customer Qualification and R&D

The Kellyton qualification line and R&D lab continue to support product development and customer evaluation. Samples in excess of 1 metric ton of CSPG have been produced for prospective customers in the EV and battery energy storage sectors, including large global lithium-ion battery manufacturers and OEMs. R&D efforts are focused on developing lower-swelling natural graphite-based anode material to address opportunities in the energy storage market, particularly for LFP chemistries.

Financial Overview

For Q2 FY26, Westwater reported a consolidated net loss of $4.3 million ($0.03 per share), compared to $3.9 million ($0.05 per share) in Q2 FY25. The net loss for the first half of 2026 was $9 million ($0.07 per share), up from $6.5 million ($0.09 per share) in H1 FY25. This increase was primarily driven by higher costs associated with Coosa permitting, stock-based compensation, and product development, partially offset by increased interest income. The company held $38.2 million in cash as of June 30, 2026.

Summary of the company's earnings call; see how call summaries are prepared. Not investment advice.