What Riot Platforms promised, and what happened

Guidance Tracker · every commitment management made on a call, tracked from the quarter it was made

Guidance

What management said, and what became of it

4 of 9 judged targets kept · 10 open · verdicts reflect calls analysed to Jun 2026.

TargetOriginal wordingSaidLatest callVerdict
AMD initial lease Phase 2 delivery (remaining 20MW of critical IT capacity at Rockdale)delivery in May 2026Dec 2025Jun 2026:We commissioned and delivered the final phase of the first 25 megawatts of capacity in May to AMD on time and on budget, with AMD operating on the site since January.
Call transcript, Jun 2026 · no direct link
Achieved
AMD lease expansion Phase 3 delivery (10MW at Rockdale)delivery in November 2026Mar 2026Jun 2026:with the initial 10 megawatts expected this November and the remaining 15 megawatts expected in May 2027.
Call transcript, Jun 2026 · no direct link
On Track
Q1 FY26 deployed hash rate forecast45 EH/sJun 2025Mar 2026:Riot produced 1,473 Bitcoin in the first quarter and ended the quarter with a deployed hash rate of 42.5 exahash.
Call transcript, Mar 2026 · no direct link
Missed

A verdict describes what became of management’s own words in later analysed calls. “Delayed” is a change of date, “went quiet” a target the calls stopped mentioning. None of it is a judgement on the investment. The methodology sets out how verdicts are recorded.

The full ledger

Open Riot Platforms’s full ledger

A free account opens 5 company ledgers a month. All 19 tracked commitments, with each call’s wording and source.

The rest of the ledger

Pro opens all 19 tracked commitments for Riot Platforms

Above is what the last two calls moved. Pro adds every quarter's revision, the source quote behind each one, and the topics management has stopped answering.