BALAMINES

What Balaji Amines promised, and what happened

Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.

Guidance record · Q4 FY26

what the last two calls moved 16 tracked 1 delivered 4 missed 11 open
  • Methylamine Commissioning delivered said Q2 FY24 Promised: Q2 FY25 Q4 FY26: Promise remains achieved.
  • FY25 EBITDA Margin missed said Q4 FY24 Promised: 21% to 24% for FY25 Q4 FY26: Promise period has passed. The final outcome remains 'missed'.
  • Dimethyl Ether Commissioning delayed said Q2 FY24 Promised: H1 FY25 Q4 FY26: Commissioning is now expected during Q1 FY27. Plant is constructed but transportation approvals are still pending.

The rest of the ledger

Above is what the last two calls moved. Pro opens all 16 tracked commitments for Balaji Amines — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.