CAPACITE
What Capacit'e Infraprojects promised, and what happened
Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.
Guidance record · Q1 FY27
what the last two calls moved 18 tracked 3 delivered 4 missed 11 open- FY26 Order Inflow delivered said Q3 FY25 Promised: 4,000 crores Q1 FY27: Promise concluded in FY26.
- FY26 Revenue Growth YoY missed said Q3 FY25 Promised: 25-30% Q1 FY27: Promise concluded in FY26.
- FY27 Revenue Growth YoY at risk said Q4 FY26 Promised: 20% Q1 FY27: Q1 revenue growth was 7% YoY, significantly below the annual target. Management maintains guidance, citing project ramp-ups in later quarters.
The rest of the ledger
Above is what the last two calls moved. Pro opens all 18 tracked commitments for Capacit'e Infraprojects — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.