What Ganesh Benzoplast promised, and what happened

Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.

Guidance record · Q4 FY26

what the last two calls moved 10 tracked 1 delivered 4 missed 5 open
  • Decision on 8.5 acres JNPT land utilization delivered said Q1 FY26 Promised: Better visibility/decision by the end of Q2 FY26. Q4 FY26: The decision to pursue LST expansion is now in the execution phase, confirming the promise was met.
  • New LPG Capex Project Execution missed said Q3 FY25 Promised: INR 900 crore LPG terminal, piling starts March 2025, completion in 2 years. Q4 FY26: No update provided. The topic of LPG/Ammonia capex was not discussed, confirming it remains shelved.
  • Commissioning of new JNPT LST capacity delayed said Q2 FY26 Promised: 30,000 tons A-class tanks commissioned within a year. Q4 FY26: Timeline for the first phase (now specified as 50,000 kL) has been pushed from Q1 FY27 to 'end of calendar year 2026' (Q3 FY27).