NHPC

What NHPC promised, and what happened

Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.

Guidance record · Q4 FY26

what the last two calls moved 12 tracked 4 delivered 1 missed 7 open
  • Subansiri Lower Commissioning (Units in FY26) delivered, diluted said Q4 FY25 Promised: We are very hopeful of commissioning 5 units of the project in the current financial year [FY26]. Q4 FY26: Management confirms they have commissioned four units of the Subansiri Lower Project by the end of FY26, meeting the revised target set in Q3.
  • Solar PPA Signing Volume went quiet said Q3 FY26 Promised: hopeful that in next 2 to 3 months, we may sign PPA of around 2,000 to 3,000 MW Q4 FY26: The target to sign 2-3 GW of solar PPAs by May 2026 was not mentioned in the Q4 earnings call. The deadline has passed with no update provided.
  • Khavda Solar Stage-3 (200 MW) Commissioning delayed said Q4 FY25 Promised: The project is expected to be commissioned by March'26. Q4 FY26: The commissioning timeline for Khavda Stage-III has been pushed from March'26 to December'26.

The rest of the ledger

Above is what the last two calls moved. Pro opens all 12 tracked commitments for NHPC — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.