PYRAMID

What Pyramid Technoplast promised, and what happened

Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.

Guidance record · Q1 FY27

what the last two calls moved 19 tracked 3 delivered 3 missed 13 open
  • Solar Plant Operations delivered, diluted said Q4 FY25 Promised: Commissioning scheduled in phases starting July 2025 Q1 FY27: Full 14.25 MW plant now commissioned, completing the project a year after the original target.
  • Recycling Plant License went quiet said Q4 FY26 Promised: We are currently awaiting the final license approval from the Pollution Control Board government agency, which is expected by June, July 2026. Q1 FY27: No confirmation of license receipt by the June/July 2026 deadline. Management only mentioned delays due to EPR portal closure.
  • Annual Power Cost Savings revised up said Q4 FY25 Promised: Reduce annual power costs by around 10% Q1 FY27: FY27 annual savings target revised back up to ₹15 Cr from ₹10 Cr. Q1 savings were ₹2 Cr.