SKIPPER
What Skipper promised, and what happened
Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.
Guidance record · Q1 FY27
what the last two calls moved 21 tracked 4 delivered 4 missed 13 open- Capacity Commissioning (75k tons) delivered said Q3 FY25 Promised: Major part in Q4 FY25, spill over to Q1 FY26 Q1 FY27: This capacity has been operational since Q1 FY26.
- FY26 Export Order Inflow missed said Q1 FY26 Promised: Double to INR 1,500-1,600 crores Q1 FY27: This target for FY26 was missed due to geopolitical challenges.
- 2nd Capacity Expansion (75k tons) delayed said Q4 FY25 Promised: Add a further 75,000 tons in FY26 Q1 FY27: the ongoing 75,000 ton capacity expansion is expected to become operational during the second half of the year, taking our total manufacturing capacity to 450,000 tons per annum.
The rest of the ledger
Above is what the last two calls moved. Pro opens all 21 tracked commitments for Skipper — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.
See what Pro opens