UTLSOLAR
What Fujiyama Power Systems promised, and what happened
Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.
Guidance record · Q1 FY27
what the last two calls moved 23 tracked 4 delivered 2 missed 17 open- Dadri Solar Cell Line Operationalization delivered said Q2 FY26 Promised: within 1 month Q1 FY27: Maintained. Promise was achieved in a previous quarter.
- Dadri Solar Cell Line Full Capacity missed said Q2 FY26 Promised: full capacity by March/April 2026 Q1 FY27: Maintained. Promise was missed in a previous quarter.
- Ratlam Facility Capacity Addition delayed said Q2 FY26 Promised: add 2,000 megawatts each of solar panels, inverters, and batteries by March 2026 Q1 FY27: The 2GW solar panel and 2GW power electronics facilities at Ratlam were commissioned. The 2GW battery capacity is on track for Q2 FY27. The original target of March 2026 for all three was missed.
The rest of the ledger
Above is what the last two calls moved. Pro opens all 23 tracked commitments for Fujiyama Power Systems — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.
See what Pro opens