Enbridge (ENB) Q2 FY25 earnings call: guidance and Q&A

Earnings call· Jun 2025 (Q2 FY25)· Energy· Aug 1, 2025

Source: earnings call transcript

Executive summary

Enbridge Q2 FY25 — Record EBITDA and Strong Growth Outlook Driven by Utility Acquisitions and Data Center Demand

Enbridge delivered a strong second quarter, achieving record EBITDA primarily due to contributions from recently acquired U.S. gas utilities and successful rate settlements. The company is effectively capitalizing on rising power demand, particularly from AI and data centers, through its diversified asset base and low-risk commercial frameworks. Management expressed confidence in meeting its full-year guidance, with a focus on disciplined capital allocation and extending its growth outlook through the end of the decade.

Highlights

5
  • Achieved record second quarter EBITDA, up 7% year-over-year, driven by U.S. gas utility acquisitions and rate settlements.

  • Mainline transported 3 million barrels per day, with strong utilization and apportionment for 6 of 8 months.

  • Sanctioned $900 million Clear Fork project, fully contracted with Meta for data center support.

  • Secured capital program increased to $32 billion, adding visibility to 5% growth through the end of the decade.

  • Debt to EBITDA decreased to 4.7x, below the midpoint of the target range.

Concerns

3
  • Ohio rate case decision was disappointing, though still resulted in a strong ROE and increased equity thickness.

  • Woodfibre LNG project experienced capital cost increases due to building codes, permitting delays, and site conditions, though contract structure protects returns.

  • Higher-than-expected U.S. interest rates partially offset tailwinds to full-year guidance.

Guidance & targets

CategoryTargetConfidence
Adjusted EBITDA
Upper end of guidance range
high materiality
High
DCF per share
Midpoint of guidance range
high materiality
High
Secured Capital Program
$32 billion
high materiality
High
Growth Outlook
5% growth
high materiality
High
Shareholder Returns
$40 billion to $45 billion
high materiality
High
Annual Investment Capacity
$9 billion to $10 billion
medium materiality
High
Mainline Optimization Phase 1 FID
Later this year
medium materiality
High
Woodfibre LNG Return on Capital
Low double-digit return
medium materiality
High
Woodfibre LNG In-Service Date
2027 to 2029 time period
medium materiality
High
Ohio Utility ROE
Almost 10%
low materiality
High
New Rates in North Carolina and Utah
By next year
low materiality
High
Sequoia Solar Partial In-Service
2025
medium materiality
High
Sequoia Solar Full Production
2026
medium materiality
High
Ohio Utility Rate Case Filing
Likely by the end of this year
low materiality
High

Segment performance

SegmentRevenueYoYQoQMargin
Liquids Pipelines
Strong volumes on the Mainline, with continued high utilization. Weaker results at FSP and Spearhead led to a slight decrease compared to 2024. The Gray Oak expansion partially entered service.
Mainline throughput: 3 million bbl/dMainline throughput (H1 FY25): 3.1 million bbl/dMainline apportionment: 6 of 8 months (including July and August)
————
Gas Transmission
Strong operational performance and revised rates on U.S. GT assets contributed to year-over-year growth. Contributions from Whistler JV, DBRS system acquisitions, and Venice Extension entering service. Sanctioned Line 31 expansion and Aitken Creek storage expansion.
—up year-over-year——
Gas Distribution and Storage
U.S. gas utility acquisitions were the main driver of growth. Higher rates, customer growth, and storage revenues in Ontario, along with colder weather, also contributed. Filed for new rates in North Carolina and Utah.
Ohio ROE: almost 10%Ontario Phase 2 rebasing: rates set through 2028
—up relative to last year——

Deals & partnerships

Consortium of 38 indigenous groups Investment in West Coast system

Backed by a loan guarantee from the Canadian government. Provides sustained economic benefits to First Nations and aligns with capital recycling goals.

Matterhorn Express pipeline Acquisition of 10% interest

Located in the Permian basin. Contributes as a tailwind to full-year guidance.

Meta Platforms Long-term offtake agreement for Clear Fork Solar long-term

Meta is a new addition to Enbridge's AI and data center-related customers.

Amazon Power Purchase Agreement (PPA) for solar power

Milestone project for solar power completed.

AT&T Power Purchase Agreement (PPA) for solar power

Milestone project for solar power completed.

Capital programs

Clear Fork project sanctioned $900 million
Start: Q2 FY25

Benefit:600-megawatt facility

Located near San Antonio, Texas. Fully contracted under a long-term offtake agreement with Meta to support data center operations. Expected to meet requirements for renewable tax credits.

Mainline investment underway up to $2 billion
Spent to date: underway
Start: Q2 FY25

Benefit:support continued high utilization, extend asset life and reliability

Investment is underway, expected to earn attractive returns within the MTS Agreement collar of 11% to 14.5%.

Mainline Expansion Phase 1 nearing FID

Benefit:150,000 barrel per day

Full path FSP open season was oversubscribed. FID expected later this year. Will fit within CTS or MTS rate base.

Line 31 expansion of Texas Eastern sanctioned
Start: Q2 FY25

Benefit:serve rising industrial and power demand

Secured under 20-year take-or-pay agreements with an investment-grade customer in Mississippi.

Aitken Creek storage facility expansion sanctioned
Start: Q2 FY25

Benefit:40 Bcf expansion

Will support the growing Canadian LNG market and optimize other expansions on the West Coast system.

SESH expansion underway $50 million
Start: Q2 FY25

Benefit:serve growing power generation needs of a major electric utility serving data centers

Part of optimization projects on the Gulf Coast.

Tres Palacios storage facility upgrade underway
Start: Q2 FY25

Benefit:increase injection and withdrawal rates

Part of a larger expansion opportunity expected later in the decade.

Sequoia Solar development underway

Benefit:815-megawatt

Project in Texas, on track to partially enter service in 2025.

Traverse Pipeline project upsizing completed

Benefit:from 1.75 Bcf per day to 2.5 Bcf per day

Upsized due to strong customer demand. Part of the Whistler JV, transporting natural gas between Agua Dulce and Katy area in Texas.

Risks & headwinds

Trade conflict, legislative change, and geopolitical volatility 2025

Markets turbulent in 2025

Mitigation:Enbridge's stable business model and low-risk commercial frameworks, with 80% of EBITDA generated by assets with revenue inflators or regulatory mechanisms, and over 98% from regulated returns or long-term take-or-pay contracts.

Commodity price volatility Q2 FY25

Continued price volatility across commodity markets

Mitigation:Enbridge's low-risk business model protected from dynamics with virtually no exposure to commodity prices.

Higher-than-expected U.S. interest rates FY25

Higher-than-expected U.S. interest rates

Mitigation:Partially offset by tailwinds like Matterhorn Express acquisition, strong Mainline volumes, and U.S./CAD exchange rate strength.

Ohio rate case decision Q2 FY25

Disappointment in Ohio rate case decision

Mitigation:Still resulted in almost 10% ROE and increased equity thickness; company filed a rehearing and plans another rate case by year-end.

Woodfibre LNG capital cost increases Ongoing

Capital cost increases

Mitigation:Contract structure allows earning a low double-digit return on capital, with the rate set closer to the in-service date. Partner (70% owner) takes capital cost risk.

What to watch in Q3 FY25

Mainline Optimization Phase 1 FID

later this year
Current Open season oversubscribed
Target FID reached

Why it matters

Sanctioning this project is key to expanding egress options for customers and securing future returns in the Liquids business.

We expect to reach FID on the first phase of the Mainline Optimization later this year.

Find out whether ENB delivers this. Inve re-checks your case every morning.

Q&A highlights

What are the opportunities for natural gas expansion to serve incremental power and data center demand across Enbridge's footprint, and what is the timeline for new projects?

Enbridge sees opportunities across all four business units (GDS, GTM, Renewables) for power demand, with 35+ opportunities on the Gas Transmission side for 11 Bcf of gas, including 10+ specific data center opportunities in late stage. 45% of North American natural gas power generation is within 50 miles of their system, along with 29 new data centers and 78 coal plants. Opportunities are primarily in the U.S., with some emerging in Canada for LNG.

“45% of all natural gas power generation is within 50 miles of our system. And within that area, too, that 50 miles, there's 29 new data centers. And then, of course, we still have the opportunities for coal to gas conversions. There's 78 coal plants in that area.”

asked by Jeremy Tonet · answered by Cynthia Hansen

3 min read 7 chapters

Detailed narrative

Strong Financial Performance and Outlook

Enbridge reported a record second quarter adjusted EBITDA, up 7% year-over-year, driven by the recent acquisitions of U.S. gas utilities and successful rate settlements in the Gas Transmission business. The company is confident in achieving the upper end of its EBITDA guidance range and meeting its DCF per share midpoint for FY25.

The balance sheet remains strong with debt to EBITDA at 4.7x as of June 30, below the target range midpoint, reflecting the full quarter contribution from the U.S. gas utility acquisitions.

Capitalizing on Growing Power Demand

Enbridge is actively pursuing opportunities related to rising power demand, particularly from AI and data centers. The company sanctioned the $900 million Clear Fork project in Texas, a 600-megawatt solar facility fully contracted with Meta Platforms. Additionally, the Line 31 expansion of Texas Eastern in Mississippi was sanctioned to serve industrial and power demand under 20-year take-or-pay agreements.

Enbridge is also working to commercialize opportunities to support data centers and hyperscalers, with over $5 billion in power demand projects serving a combined 6 gigawatts of new generation.

Liquids Business Optimization and Growth

The Liquids business demonstrated strong performance, with the Mainline transporting 3 million barrels per day in Q2 and 3.1 million barrels per day for the first half of 2025. The company is investing up to $2 billion in the Mainline through 2028 to support utilization and extend asset life, expecting attractive returns within the MTS Agreement collar of 11% to 14.5%.

An open season for the Flanagan South Pipeline was oversubscribed, and FID for the 150,000 barrel per day Mainline Expansion Phase 1 is expected later this year. The Gray Oak expansion has partially entered service, with full commercial operation expected in mid-2026.

Gas Transmission Expansions

In Gas Transmission, Enbridge sanctioned the Line 31 expansion of Texas Eastern and a 40 Bcf expansion of the Aitken Creek storage facility to support the growing Canadian LNG market. Optimization projects include a $50 million expansion of SESH to serve power generation for data centers and an upgrade to the Tres Palacios storage facility.

The company noted that Texas Eastern Transmission will be interconnected to the Homer City Redevelopment generating facility in Pennsylvania, highlighting ongoing efforts to serve industrial, power, and LNG demand.

Gas Distribution and Regulatory Landscape

The Gas Distribution business continues to provide foundational growth. The Phase 2 rebasing process in Ontario was completed, setting rates through 2028. In Ohio, a rate case decision resulted in an almost 10% ROE and increased equity thickness, despite not meeting all requests.

The company has filed for new rates in North Carolina and Utah, expecting decisions by next year. An impairment related to the Ohio utility was primarily due to the treatment of pension assets, which the company is appealing.

Renewable Power Portfolio Advancement

Enbridge is advancing its renewable portfolio, sanctioning the 600-megawatt Clear Fork Solar project in Texas, which is fully contracted with Meta Platforms and expected to qualify for U.S. renewable tax credits. The 815-megawatt Sequoia Solar development is on track for partial service in 2025 and full production in 2026.

The company believes recent U.S. legislative changes enhance the value of its late-stage development projects, and it continues to secure PPAs with major corporations like Amazon and AT&T.

Disciplined Capital Allocation and Shareholder Returns

Enbridge maintains a focus on disciplined capital allocation, with a secured capital program of $32 billion supporting 5% growth through the end of the decade. The company expects to return $40 billion to $45 billion to shareholders over the next five years, underpinned by its 30 consecutive years of dividend increases.

Investment decisions prioritize low multiple brownfield and utility-like projects, with an annual investment capacity of $9 billion to $10 billion. The company also recycled capital by closing an investment on its West Coast system by indigenous groups, generating $0.7 billion in cash proceeds.

Summary of the company's earnings call; see how call summaries are prepared. Not investment advice.