TC Energy (TRP) Q2 FY25 earnings call: guidance and Q&A

Earnings call· Jun 2025 (Q2 FY25)· Utilities· Jul 31, 2025

Source: earnings call transcript

Executive summary

TC Energy Q2 FY25 — Strong EBITDA Growth and Project Execution

TC Energy delivered strong Q2 FY25 results, driven by robust project execution and increased demand across its natural gas and power portfolios. The company raised its 2025 comparable EBITDA outlook and remains on track for its deleveraging target by the end of 2026, underpinned by a disciplined capital allocation strategy focused on brownfield expansions and high-return opportunities. Management highlighted significant growth potential from increasing North American natural gas demand, particularly from LNG exports and data centers, reinforcing confidence in future project announcements.

Highlights

5
  • Comparable EBITDA increased 12% year-over-year in Q2 FY25.

  • 2025 comparable EBITDA outlook raised to $10.8 billion to $11 billion, representing a 9% increase over 2024.

  • Completed or placed into service approximately $5.8 billion of capacity projects, including Southeast Gateway.

  • Sanctioned projects achieved an average unlevered after-tax IRR of 12% year-to-date FY25.

  • Bruce Power achieved 98% availability in Q2 FY25, with realized power price up $8/MWh year-over-year to $110/MWh.

Concerns

2
  • Lower Alberta power prices averaged approximately $40 per megawatt hour in Q2 FY25.

  • Lower equity earnings from Sur de Texas due to strengthening peso and higher income tax expense in Q2 FY25.

Guidance & targets

CategoryTargetConfidence
Comparable EBITDA
$10.8 billion to $11 billion
high materiality
High
Assets into service
approximately $8.5 billion
high materiality
High
Leverage (Net Debt/EBITDA)
approximately 4.75x
high materiality
High
EBITDA
$11.7 billion to $11.9 billion
high materiality
High
Bruce Power availability
low 90% range
medium materiality
High
Methane intensity reduction target
40% to 55%
low materiality
High
EBITDA build multiples for new projects
5x to 7x range
medium materiality
High
IRRs for new projects
low to mid-teens
medium materiality
High
Bruce Power equity income
nearly double
medium materiality
High
North American natural gas demand growth
45 Bcf per day
high materiality
High

Segment performance

SegmentRevenueYoYQoQMargin
Power and Energy Solutions
Had higher contributions from Bruce due to increased generation output and a higher average realized price (up $8/MWh YoY). Alberta co-gen delivered strong performance with over 90% availability, maximizing capacity payments. Partially offset by lower Alberta power prices averaging approximately $40/MWh.
Bruce Power availability: 98%Bruce Power realized price: $110 per megawatt hourAlberta co-gen availability: >90%
————

TRP operating KPIs by quarter

TRP operating KPIs stated on its earnings calls, by fiscal quarter
KPIThis call Jun 2025 Q2 FY25 Sep 2025 Q3 FY25Change vs prior quarter
Availability Bruce Power
98% On the bottom of the slide, in our Power and Energy Solutions business, Bruce achieved 98% availability in an exceptionally strong quarter while also receiving its annual price adjustment as of April 1. Source: earnings call transcript
94% In our Power and Energy Solutions business, Bruce Power achieved 94% availability, which includes the planned outages on Units 3 and 4 and is in line with our expected annual availability in the low 90% range for full year 2025. Source: earnings call transcript
-4 pt

Operating figures the company stated on at least two of the calls shown, checked against each call's transcript. Click a figure to read the sentence. A dash means it was not stated that quarter.

Deals & partnerships

Saugeen Ojibway Nation (SON) Equity partnership in OPS (Ontario Power Generation)

Working closely with SON as equity partners on the OPS project.

OMERS Partner on Bruce Power

Partners with OMERS on Bruce Power.

Various partners Partners on Coastal GasLink (CGL)

Numerous partners involved in the Coastal GasLink project.

Capital programs

Assets into service underway $8.5 billion
Spent to date: $5.8 billion
Start: FY25

Benefit:3 Bcf per day of incremental capacity

Expected to be placed into service in 2025, with $5.8 billion already completed or placed into service, including Southeast Gateway and East Lateral XPress. Tracking approximately 15% below budget.

Bruce C Project development progressing
Funding: federal funding

Supported by up to $50 million in federal funding for development and assessment. Final Investment Decision (FID) not expected until early 2030.

Risks & headwinds

Lower Alberta power prices Q2 FY25

averaged approximately $40 per megawatt hour

Lower equity earnings from Sur de Texas Q2 FY25

due to strengthening peso and higher income tax expense

Planned maintenance outage Q3 FY25

Unit 2

Mitigation:Factored into full-year Bruce Power availability guidance of low 90% range.

FX volatility long-term

A $0.01 change in USD-CAD corresponds to roughly a $0.01 change in comparable EPS (unhedged)

Mitigation:Systematically hedges U.S. dollar net income to insulate comparable earnings from FX volatility.

What to watch in Q3 FY25

Columbia Gas rate settlement details

Next quarter
Current 26% increase in pre-filed FTS rates (interim)
Target Final settlement details, including step-up in rates for three defined periods

Why it matters

Provides clarity on future revenue streams from a key U.S. natural gas asset.

The rates obviously are subject to final settlement once we have filed and seen approval by FERC. There were several key issues that were addressed by the settlement in principle, including the establishment of rates for three defined periods, also 3-year moratorium and a required comeback in 6 years and roll-in treatment for a couple of our recent reliability projects. Related to your question on the step-up in rates, that is not detailed in the settlement at this stage, and the step-up in that detail of rates is going to be provided in the final filing.

Find out whether TRP delivers this. Inve re-checks your case every morning.

Q&A highlights

Can you provide more details on the three defined periods for rates and the conditions/magnitude of rate step-ups in the Columbia Gas settlement?

The interim settlement reflects a 26% increase in pre-filed FTS rates, effective April 1. While three defined periods are established, specific details on rate step-ups will be provided in the final filing, which is subject to FERC approval.

“The rates obviously are subject to final settlement once we have filed and seen approval by FERC. There were several key issues that were addressed by the settlement in principle, including the establishment of rates for three defined periods, also 3-year moratorium and a required comeback in 6 years and roll-in treatment for a couple of our recent reliability projects. Related to your question on the step-up in rates, that is not detailed in the settlement at this stage, and the step-up in that detail of rates is going to be provided in the final filing.”

asked by Praneeth Satish · answered by Tina Faraca

3 min read 6 chapters

Detailed narrative

Natural Gas Demand Growth and Data Center Opportunities

TC Energy has revised its long-term forecast for North American natural gas demand growth to 45 Bcf per day by 2035, up from a prior forecast of 40 Bcf per day. This increase is primarily driven by LNG exports, power generation, and industrial demand, including the accelerating needs of AI and data centers.

The company is actively engaged in commercial conversations with over 30 counterparties across the data center value chain, with some indicating potential for greater capacity requirements than originally planned, reinforcing confidence in future project announcements.

Project Execution and Capital Efficiency

The company has completed or placed into service approximately $5.8 billion of capacity projects year-to-date, including Southeast Gateway and the East Lateral XPress Project. TC Energy expects to place a total of $8.5 billion of assets into service in 2025, approximately 15% below budget.

The average unlevered after-tax IRR for sanctioned projects has steadily increased, reaching 11% in 2024 (up from 8.5% a few years ago) and 12% year-to-date 2025. New projects are expected to deliver EBITDA build multiples in the 5x to 7x range, translating to low to mid-teens IRRs.

Columbia Gas Rate Settlement

TC Energy reached a settlement in principle with customers on its Columbia Gas system, which is expected to result in a 26% increase in pre-filed FTS rates, effective April 1. This outcome underscores strong demand and effective collaboration with stakeholders.

The settlement establishes interim rates and outlines three defined periods for rates, with further details on step-ups to be provided in the final filing, subject to FERC approval.

Bruce Power Performance and Outlook

Bruce Power delivered strong performance in Q2 FY25 with 98% availability and an annual price adjustment, resulting in a realized power price of $110 per megawatt hour, up $8 per megawatt hour year-over-year. The company expects full-year 2025 availability to be in the low 90% range, including a planned Unit 2 maintenance outage in Q3.

Investments through the major component replacement program and Project 2030 are expected to nearly double equity income from Bruce Power by 2035, supporting Ontario's clean energy goals.

Capital Allocation and Deleveraging

TC Energy is focused on maximizing value from its assets and executing its high-quality, capital-efficient growth portfolio. The company expects to deleverage to approximately 4.75x by the end of 2026, down from a projected 2025 peak of 4.9x, driven by full-year contributions from new projects.

Discretionary capital allocation will predominantly favor the U.S. due to higher risk-adjusted returns, with a focus on brownfield, in-corridor expansions averaging around $450 million per project.

Canadian Energy Policy and NGTL Growth

Management views Bill C-5 as a positive development, indicating federal government support for Canada's role as an energy superpower. The company is working with LNG Canada on a bona fide estimate for a potential Phase 2 expansion of Coastal GasLink.

The NGTL multiyear growth program has $700 million committed under a $3.3 billion framework, with a cadence of projects expected to increase egress from the basin, honoring commitments to Canadian customers while balancing capital allocation with higher-return opportunities elsewhere.

Summary of the company's earnings call; see how call summaries are prepared. Not investment advice.