ADANIPOWER
What Adani Power promised, and what happened
Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.
Guidance record · Q1 FY27
what the last two calls moved 19 tracked 0 delivered 2 missed 17 open- Dhirauli Coal Mine Production Start went quiet said Q1 FY26 Promised: Begin production by September-October 2025 Q1 FY27: Not mentioned in the earnings call or presentation.
- Operating Capacity Target revised up said Q2 FY24 Promised: ~6,000 MW additional over current 15,000 MW Q1 FY27: Target revised up to 45 GW by the same timeline as the previous 42 GW target.
- Mahan Phase 2 Commissioning Timeline delayed said Q4 FY25 Promised: March-April 2027, followed by one 800 MW unit every 6 months Q1 FY27: First unit scheduled for commercial operation in Q1 FY28. Second unit in Q3 FY28, with efforts to bring it to Q2 FY28. This confirms the previously delayed timeline.
The rest of the ledger
Above is what the last two calls moved. Pro opens all 19 tracked commitments for Adani Power — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.