COALINDIA
What Coal India promised, and what happened
Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.
Guidance record · Q4 FY25
what the last two calls moved 7 tracked 1 delivered 1 missed 5 open- FY25 Production missed said Q2 FY24 Promised: 840-850 million tonnes Q4 FY25: FY25 volumes nearly flat, missed target significantly
- Long-term Production Target delayed said Q1 FY23 Promised: 1 billion tonnes by FY25 Q4 FY25: Plateau of 1 BT to 1.043 BT now expected by FY29-30
- FY26 Production open said Q4 FY25 Promised: 875 million tonnes Q4 FY25: 875 million tonnes