ENDURANCE
What Endurance Technologies promised, and what happened
Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.
Guidance record · Q1 FY27
what the last two calls moved 23 tracked 3 delivered 2 missed 18 open- Battery Pack Manufacturing Plant SOP delivered, diluted said Q4 FY25 Promised: The SOP is planned in January 2026. Q1 FY27: Commenced SOP for Hero MotoCorp in June 2026.
- Europe Capex FY26 missed said Q1 FY26 Promised: Maximum of €20-25 million. Q1 FY27: No new update, considered missed.
- AURIC Shendra Plant SOP Timeline delayed said Q3 FY25 Promised: SOP is planned for June 2025 Q1 FY27: SOP will start in September 2026.
The rest of the ledger
Above is what the last two calls moved. Pro opens all 23 tracked commitments for Endurance Technologies — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.