GPIL
What Godawari Power And Ispat promised, and what happened
Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.
Guidance record · Q1 FY27
what the last two calls moved 31 tracked 3 delivered 5 missed 23 open- Pellet Plant Capacity Expansion delivered said Q3 FY25 Promised: Commissioning of 4.7 million tons total capacity by Q2 FY26 Q1 FY27: Achievement re-confirmed. One plant was shut down due to high gas prices, but this is an operational issue, not a capacity reduction.
- Ari Dongri Mining Capacity missed said Q3 FY25 Promised: 6 million tons capacity approval by Q1 FY26 Q1 FY27: Full scale operation is now targeted from FY '28, with ramp-up from Q3 FY27. This confirms the original target for Q1 FY26 was missed.
- Total Pellet Production FY27 revised down said Q3 FY25 Promised: 4.5 million tons Q1 FY27: Management is evaluating a further cut to the 4.0 million ton guidance due to a plant shutdown caused by high gas prices, making operations unviable.
The rest of the ledger
Above is what the last two calls moved. Pro opens all 31 tracked commitments for Godawari Power And Ispat — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.