Guidance record · Q1 FY27

what the last two calls moved 17 tracked 2 delivered 2 missed 13 open
  • Renewable Energy Capacity went quiet said Q3 FY25 Promised: 31 GW by 2030 Q1 FY27: No mention of the 31 GW by 2030 target. A new, shorter-term target of 18 GW by FY30/31 was introduced.
  • Barauni Refinery Expansion Date delayed said Q3 FY25 Promised: next financial year end (FY26-27) Q1 FY27: Revised to December 2026 from August 2026.
  • FY26 CAPEX delivered said Q3 FY25 Promised: INR 33,000 crores Q4 FY26: Achieved: FY26 capex was 31,401 cr, within the 30k-40k cr guidance.