LLOYDSME

What Lloyds Metals And Energy promised, and what happened

Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.

Guidance record · Q1 FY27

what the last two calls moved 20 tracked 5 delivered 2 missed 13 open
  • Mining EC Approval delivered said Q3 FY25 Promised: EC approval for 25 MT expected in 60-70 days Q1 FY27: Milestone complete, no further updates required.
  • Thriveni FY26 EBITDA missed said Q2 FY26 Promised: Revised down from INR 2,800 crores to INR 2,000-2,200 crores Q1 FY27: Target period concluded. Final result was INR 1,990 crores vs target of INR 2,000-2,200 crores.
  • BHQ Beneficiation Plant Phase 1 delayed said Q3 FY25 Promised: First phase completed by '27 Q1 FY27: Timeline delayed to March '28 (end of Q4 FY28).

The rest of the ledger

Above is what the last two calls moved. Pro opens all 20 tracked commitments for Lloyds Metals And Energy — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.