PREMEXPLN
What Premier Explosives promised, and what happened
Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.
Guidance record · Q1 FY27
what the last two calls moved 15 tracked 2 delivered 1 missed 12 open- EBITDA Margin delivered, diluted said Q4 FY25 Promised: 15% to 20% Q1 FY27: Promise concluded in FY26. Final verdict remains 'achieved_diluted'.
- FY26 Revenue missed said Q4 FY25 Promised: INR 600 crores Q1 FY27: Promise concluded in FY26. Final verdict remains 'missed'.
- RDX/HMX Plant Expansion Production delayed said Q1 FY26 Promised: Before December 2025 Q1 FY27: Timeline delayed again. Management now expects to take up water trials in September (Q2 FY27), with production to start after that, pushing commissioning into Q3 FY27.
The rest of the ledger
Above is what the last two calls moved. Pro opens all 15 tracked commitments for Premier Explosives — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.