SANATHAN
What Sanathan Textiles promised, and what happened
Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.
Guidance record · Q1 FY27
what the last two calls moved 20 tracked 1 delivered 3 missed 16 open- Punjab Phase 1 Capex Cost missed said Q3 FY25 Promised: INR 1,850 crores Q1 FY27: No new information provided on the final cost. Focus has shifted to new capex projects (MP plant).
- Technical Textile Capacity (18,000 MTPA) delayed said Q3 FY25 Promised: Coming year (FY26) Q1 FY27: Installation completed, but commissioning is 'very shortly' as of early Q2. Missed the 'end of Q1 FY27' target.
- Punjab Phase 1 Capacity (700 TPD) delivered said Q3 FY25 Promised: Operational by Q1 FY26 Q4 FY26: Ramped up to the end of first phase (700 TPD) by the end of March.
The rest of the ledger
Above is what the last two calls moved. Pro opens all 20 tracked commitments for Sanathan Textiles — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.
See what Pro opens