SARDAEN

What Sarda Energy & Minerals promised, and what happened

Every commitment management made on a call, tracked from the quarter it was made — reaffirmed, revised, diluted or quietly dropped.

Guidance record · Q1 FY27

what the last two calls moved 16 tracked 1 delivered 5 missed 10 open
  • Rehar Hydropower Project Commissioning delivered, diluted said Q3 FY25 Promised: 25 MW Operational by end of FY25 Q1 FY27: The project remains operational and contributing to the energy segment's performance.
  • SKS Power PLF went quiet said Q3 FY25 Promised: 80-85% on annual basis Q1 FY27: The annual PLF for FY26 was not reported. Management mentioned 'improvement in the power capacity utilization in our IPP' as a future growth driver but did not address the past target.
  • Captive Solar Power Project Commissioning delayed said Q2 FY25 Promised: 50 MW operational by end of FY25 Q1 FY27: Commissioning delayed again due to right-of-way issues. New target is 'before the end of the next quarter' (Q2 FY27).

The rest of the ledger

Above is what the last two calls moved. Pro opens all 16 tracked commitments for Sarda Energy & Minerals — every quarter's revision, the source quote behind each one, and the topics management has stopped answering.

See what Pro opens