BRGIL B.r.goyal Infrastructure Q2 FY26 results (Jul–Sep 2025) and concall
Management summary
- B.R.Goyal Infra reported a strong H1 FY26 with record turnover and significant PAT growth, driven by robust order inflows and efficient execution.
- The order book expanded by 73% YoY, providing substantial revenue visibility.
- While operating cash flow was negative in H1 due to project investments, management anticipates it will turn positive by the fiscal year-end, maintaining a positive outlook for the infrastructure sector.
Source: Inve concall analysis and management guidance record.
Highlights
-
Highest ever H1 consolidated turnover of ₹342 crores, reflecting 60.56% YoY growth from ₹213 crores in H1 FY25.
-
Profit after tax (PAT) grew to ₹16 crores in H1 FY26, up from ₹6 crores in H1 FY25, indicating strong profitability improvement.
-
Order book grew 73% YoY to ₹1,535 crores as of September 30, 2025, providing strong revenue visibility for the next two years.
-
Secured new orders worth ₹582.45 crores in H1 FY26 across roads, buildings, wastewater, and toll collection.
What they filed
Q2 FY26: revenue up 44.3%, net profit up 300.0% against the same quarter last year.
| Line item | Q2 FY24 | Q4 FY24 | Q2 FY25 | Q4 FY25 | Q2 FY26 |
|---|---|---|---|---|---|
| Revenue | 237 | 352 | 213 | 297 | 342 +44% |
| EBITDA | 7 | 25 | 12 | 29 | 27 +286% |
| Net profit | 4 | 18 | 6 | 19 | 16 +300% |
How to read this
₹ crore, as filed. The percentage beside a figure is the change against the same quarter a year earlier — never the quarter before, which would make every seasonal business look like it collapses and booms each year.
Guidance & targets
2Revenue
Revenue Growth Revenue · FY26 · High confidence 35-40%
H2 FY26 Turnover Revenue · H2 FY26 · High confidence ₹400-450 crores
Source: Inve Guidance Tracker — management targets and direct quotes from the earnings call transcript.
Q&A highlights
2Toll Plaza Project Evaluation and Bid Pipeline Direct
we look at three different aspects when we are bidding for a plaza. First, we collect our data manually... Then, we match those data with the banking which has been done in the past from that plaza and the data provided by the government authorities. We compile these three data a
Provides insight into the company's rigorous data-driven approach for bidding on toll collection contracts, including manual data collection and cross-verification.
Asked by Tej Pal Singh
Management of Increased Receivables and Working Capital Cycle Direct
working capital cycle is around 45 days to 60 days and in comparison to turnover, if you compare then the working capital cycle and debt receivables have not increased by a percentage, but in absolute terms, it has increased because of the increase in turnover. That's why. So, th
Addresses concerns about rising receivables, clarifying that the increase is proportional to turnover growth and the working capital cycle remains healthy, mitigating a potential red flag for investors.
Asked by Tej Pal Singh
Unlock risks & concerns, Q3 FY26 watchlist, and full call analysis
You’re reading a preview. Opening the full call uses 1 concall credit and unlocks:
- 5 risks, concerns & management red flags
- 5 watchlist triggers for Q3 FY26
- +9 more guidance targets & verbatim management quotes
- +6 more analyst Q&A exchanges & evasion checks
- Capital allocation & full section-by-section narrative
Sign in to use your monthly call allowance.
Inve summary of a publicly available earnings call transcript; see how call summaries are prepared and our regulatory disclaimer. · Share on WhatsApp · Scorecard image