Skip to content

    Sagar Cements Limited

    SAGCEM
    Construction Materials·22 Jan 2026
    Management Summary

    Sagar Cements reported an 8% YoY volume growth and a 5% revenue increase to ₹591 crore in Q3 FY26, but recorded a loss after tax of ₹64 crore. EBITDA remained flat at ₹38 crore, with EBITDA per tonne at ₹254. The company is focused on cost reduction initiatives, including commissioning a new preheater at Dachepalli and progressing WHRS and grinding mill projects, which are expected to improve profitability and reduce costs per tonne in the coming quarters. Management anticipates monetizing Vizag land for approximately ₹350 crore net over the next 18 months, primarily to reduce debt and improve the debt-equity ratio.

    Highlights

    5
    • Volume growth of 8% YoY in Q3 FY26, indicating demand pickup after monsoons.

    • Revenue increased by ~5% to ₹591 crore in Q3 FY26 compared to ₹564 crore in Q3 FY25.

    • Power and fuel costs reduced to ₹1,408 per tonne from ₹1,456 per tonne in Q3 FY25, and freight costs to ₹830 per tonne from ₹835 per tonne.

    • Successful commissioning of 6-stage preheater at Dachepalli, with Andhra Cements expected to break even in Q4 FY26.

    • Strategic projects like Gudipadu WHRS (4.35 MW) and Jeerabad grinding mill expected to yield significant cost savings of ₹100-125/tonne and ₹150-200/tonne respectively.

    Concerns

    4
    • Loss after tax of ₹64 crore in Q3 FY26.

    • EBITDA for Q3 FY26 remained flat at ₹38 crore, with EBITDA per tonne at ₹254, same as Q3 FY25.

    • Only ₹5-10 price increase realized in the trade segment in January across South states, despite efforts for ₹15-20, due to festivals like Pongal.

    • Vizag land monetization, expected to yield ₹350 crore net, is dependent on final government policy and will be spread over the next 18 months.

    Key financials

    Single quarter

    06 metrics
    1. 01Revenue₹591 Cr+4.8%YoY
    2. 02EBITDA₹38 Cr0%YoY
    3. 03EBITDA per tonne₹254
    4. 04Loss after tax₹64 Cr
    5. 05Power and fuel costs per tonne₹1,408-3.3%YoY

    Capital allocation

    3
    high confidence
    CategoryHeadline
    Capex

    ₹489 crores

    Debt

    Gross ₹1,627 crores · Net ₹1,450 crores

    Liquidity

    Cash ₹83 crores

    Company expects to monetize Vizag land for a net of ₹350 crore over the next 18 months, which will be used to retire debt.

    Guidance & targets

    14
    CategoryTargetPriority
    Volume
    Overall volumes
    6 million tonnes
    High
    Volume
    Overall volumes
    7 million tonnes
    High
    EBITDA
    EBITDA per tonne
    ₹550
    High
    EBITDA
    EBITDA per tonne
    ₹500-525
    High
    Projects Commissioning
    Gudipadu WHRS
    Commissioned
    High
    Projects Commissioning
    Jeerabad capacity expansion
    Commissioned
    High
    Projects Commissioning
    Dachepalli cement capacity addition
    Commissioned
    High
    Cost Reduction
    Gudipadu WHRS savings
    ₹100-125 per tonne
    High
    Cost Reduction
    Jeerabad grinding mill savings
    ₹150-200 per tonne
    High
    Cost Reduction
    Andhra grinding plant savings
    ₹25-50 per tonne
    High
    Fuel Price
    Fuel price increase
    2-3%
    Medium
    Debt
    Debt equity ratio
    Closer to 0.5
    High
    Capacity
    Medium-term capacity target
    12 million tonnes
    High
    Capacity
    CapEx for 12-15 million tonnes
    Start
    High

    What to watch in Q3 FY26

    5

    Andhra Cements Breakeven/Profitability

    Next quarter (Q4 FY26)
    CurrentVery close to breakeven in Q3 FY26
    TargetBreakeven or profitable in Q4 FY26

    Why it matters

    Indicates successful turnaround and contribution from new preheater, impacting overall company profitability.

    I think in the current quarter itself, we expect Andhra to break even. With the better prices, we hope it should become profitable in the current quarter itself.

    Risks & concerns

    3
    RiskSeverity

    Pricing Volatility

    Price volatility led to a revision in FY26 volume guidance, and only limited price increases were realized in the trade segment in January.Management acknowledged

    medium

    Regional Demand Seasonality

    Extended monsoons in early Q3 led to subdued demand, though it picked up later in the quarter.Management acknowledged

    low

    Delay in Vizag Land Monetization

    Monetization of Vizag land is dependent on final government policy and will be spread over the next 18 months, not expected this financial year.Management acknowledged

    low

    Q&A highlights

    8

    “Now let us talk of the current financial year's outlook, it is 6 million. And we did indicate in the past that these are subject to some corrections basis the price. The price has been volatile. So basis that, from 5.8 million, we re-revised it to 6 million. So we are holding it to the 6 million now. It should roughly translate a year-on-year number of close to around 9%. Going to the next year number, yeah, we are holding at this point of time for a 7 million outlook for the coming financial year.”

    Management confirmed revised FY26 volume guidance to 6MT (up from 5.8MT) and maintained FY27 target of 7MT, providing clarity on future growth trajectory.

    asked by Shravan Shah

    3 min read7 chapters

    Detailed Narrative

    01

    Q3 FY26 Performance and Market Dynamics

    Sagar Cements reported an 8% year-on-year volume growth in Q3 FY26, contributing to a 5% increase in revenue, which reached ₹591 crore. Despite this growth, the company recorded a loss after tax of ₹64 crore, with EBITDA remaining flat at ₹38 crore, translating to an EBITDA per tonne of ₹254. Management noted that demand, initially subdued due to extended monsoons, picked up towards the latter half of the quarter, and expects to end FY26 with overall volumes of around 6 million tonnes.

    02

    Cost Optimization and Efficiency Initiatives

    The company is actively implementing various cost reduction initiatives. Power and fuel costs per tonne decreased to ₹1,408 in Q3 FY26 from ₹1,456 in Q3 FY25, while freight costs also marginally reduced to ₹830 per tonne. Key projects include the successful commissioning of a 6-stage preheater at Dachepalli and the expected commissioning of a 4.35-megawatt Waste Heat Recovery project at Gudipadu by end of FY26, which is projected to save ₹100-125 per tonne.

    03

    Capacity Expansion and Project Timelines

    Sagar Cements is progressing with its capacity expansion plans. The expansion of Jeerabad capacity from 1 million to 1.5 million tonnes is expected to be commissioned by early Q1 FY27. Additionally, cement capacity addition at Dachepalli is slated for August 2026. A new grinding mill at Jeerabad is also anticipated to contribute to operating leverage, potentially saving ₹150-200 per tonne, while an Andhra grinding plant is expected to yield ₹25-50 per tonne in savings.

    04

    Andhra Cements Turnaround and Profitability Outlook

    The Andhra Cements unit has shown significant operational improvements following the commissioning of its new preheater. The unit's specific consumption for clinker is now below Mattampally at sub 720 Kcal/kg, with electrical units at 51 units. Management expressed confidence that Andhra Cements, which was very close to breakeven in Q3, is expected to achieve breakeven or become profitable in Q4 FY26, positively impacting the company's overall financial performance.

    05

    Debt Management and Asset Monetization Strategy

    As of December 31, 2025, the company's gross debt stood at ₹1,627 crore, with a debt-equity ratio of 0.78:1. Sagar Cements plans to monetize its Vizag land, anticipating a net realization of approximately ₹350 crore over the next 18 months. These proceeds are primarily earmarked for debt reduction, with the strategic goal of bringing the debt-equity ratio closer to 0.5 within 18-24 months, enhancing financial stability.

    06

    Volume and Profitability Guidance

    For FY26, the company has revised its volume outlook to 6 million tonnes, representing approximately 9% year-on-year growth, and projects 7 million tonnes for FY27. Management is targeting an EBITDA per tonne of ₹550 for Q4 FY26 and ₹500-525 for the full FY26, including incentives. Recent price increases in the non-trade segment (₹15-20) and modest increases in the trade segment (₹5-10) are expected to support this profitability outlook.

    07

    Capital Expenditure and Future Capacity Plans

    The total capital expenditure for FY26 is projected to be ₹489 crore, with ₹303 crore spent in the first nine months and ₹186 crore budgeted for Q4. For FY27, the budgeted CapEx is ₹291 crore. The company does not foresee any major large CapEx plans for the next 2.5 to 3 years, beyond maintenance and ongoing projects. Significant capacity expansion CapEx, aimed at increasing capacity from 12 million to 15 million tonnes, is expected to commence only by end of FY28 or early FY29.

    This is an AI-generated summary of a publicly available earnings call transcript. It is for informational purposes only and does not constitute investment advice, a recommendation, or an endorsement. inve.money is not a SEBI-registered investment advisor. Please consult a qualified financial advisor before making any investment decisions.