Sagar Cements Limited Q1 FY27
What went well
- Delivered a healthy volume growth of around 13% during the quarter, reflecting resilient demand.
- Revenue increased by 5% year-on-year, driven primarily by higher volumes.
- Successfully commissioned the remaining 1.55 MW waste heat recovery at Gudipadu and completed 0.5 million tonne capacity expansion at Jeerabad.
What to watch
- Profitability and margins moderated during Q1 due to elevated input prices across energy, fuel, and packaging.
- Pricing momentum moderated towards the end of the quarter amid competitive intensity and regional market dynamics.
What Sagar Cements Limited does
Sagar Cements Limited manufactures and sells cement, operating integrated and grinding units in Telangana, Andhra Pradesh, Odisha and Madhya Pradesh that supply markets across southern, central and eastern India. Its product range spans Ordinary Portland Cement, Portland Pozzolana Cement, Portland Slag Cement, Sulphate Resistant Cement, Composite Cement and GGBS, distributed through a network of dealers and sub-dealers. The company runs captive thermal, solar, hydro and waste-heat-recovery power plants alongside its cement lines, and is setting up a new Superfine Building Materials division to make high-performance GGBS- and fly-ash-based products for precision construction.
Segments
- Cement
- Installed cement capacity
- 10.50 MTPA
- Clinker capacity
- 7.16 MTPA
- Manufacturing plants
- 6 plants — Mattampally (Telangana), Bayyavaram, Gudipadu & Dachepalli (Andhra Pradesh), Jeerabad (Madhya Pradesh), Jajpur/Kalinganagar (Odisha)
- Limestone reserves
- 1,030 million tonnes
- Total captive power capacity
- 108.98 MW
- Green captive power capacity (solar, hydro, WHRS)
- 36 MW
Guidance record · Q1 FY27
what the last two calls moved 21 tracked 4 delivered 6 missed 11 open- FY26 Sales Volume delivered said Q1 FY26 Promised: around 6 million tonnes Q1 FY27: The target period for this promise has passed. The final verdict remains 'achieved'.
- FY26 EBITDA per tonne missed said Q1 FY26 Promised: around ₹600 per tonne as a minimum Q1 FY27: The target period for this promise has passed. The final verdict remains 'missed'.
- Vizag Land Monetization delayed said Q1 FY26 Promised: Approval by Oct, ₹100-150 cr in FY26 Q1 FY27: The final government approval is still awaited. Management now expects a generic GO for all industrial lands instead of a case-specific one, further extending the uncertainty. The target of realizing ₹150 cr in FY27 remains, but is contingent on this approval.
All 21 tracked — every revision, and every one management stopped mentioning.
Open the guidance ledgerQuarterly results
Q1 FY27: revenue up 5.2%, net profit down 500.0% against the same quarter last year.
| Line item | Q2 FY25 | Q3 FY25 | Q4 FY25 | Q1 FY26 | Q2 FY26 | Q3 FY26 | Q4 FY26 | Q1 FY27 |
|---|---|---|---|---|---|---|---|---|
| Revenue | 475 | 564 | 658 | 671 | 602 +27% | 591 +5% | 787 +20% | 706 +5% |
| EBITDA | 20 | 38 | 37 | 121 | 51 +155% | 38 +0% | 82 +122% | 72 −40% |
| Net profit | -57 | -54 | -73 | 7 | -44 +23% | -64 −19% | 100 +237% | -28 −500% |
How to read this
₹ crore, as filed. The percentage beside a figure is the change against the same quarter a year earlier — never the quarter before, which would make every seasonal business look like it collapses and booms each year.
Performance −48.0% 1Y
1Y: ₹281.1 on 10 Sept 2025 → ₹146.25. High ₹281.65 (11 Sept 2025), low ₹146.25 (11 Sept 2026).
How the price took the results
close before → close after
- Q1 FY27
- −2.7%
- 28 Jul
- Q4 FY26
- +4.0%
- 14 May
- Q3 FY26
- +1.6%
- 22 Jan
- Q2 FY26
- −5.9%
- 24 Oct
The move from the last close before each results date to the first close after it — the market's first read on the quarter, not the quarter itself.
Financials, as filed
Revenue grew 5.9% a year over 3 years, FY23 to FY26. Operating margin widened to 11.0%.
| Year ending | FY23 | FY24 | FY25 | FY26 |
|---|---|---|---|---|
| Revenue | ₹2.2k Cr | ₹2.5k Cr | ₹2.3k Cr | ₹2.7k Cr |
| Operating profit | ₹154 Cr | ₹245 Cr | ₹142 Cr | ₹292 Cr |
| Operating margin | 6.9% | 9.8% | 6.3% | 11.0% |
| Interest | ₹201 Cr | ₹185 Cr | ₹187 Cr | ₹196 Cr |
| Depreciation | ₹157 Cr | ₹214 Cr | ₹231 Cr | ₹240 Cr |
| Net profit | ₹7 Cr | ₹-51 Cr | ₹-216 Cr | ₹-1 Cr |
| Net margin | 0.3% | -2.0% | -9.6% | 0.0% |
| Cash from operations | ₹175 Cr | ₹400 Cr | ₹234 Cr | ₹216 Cr |
| Free cash flow | ₹59 Cr | ₹200 Cr | ₹104 Cr | ₹-201 Cr |
| ROCE | 7.0% | 1.0% | -2.0% | 2.0% |
How to read this
From the company's own filings. Margins are computed from the filed sums; a year with an incomplete quarter is left blank rather than estimated.
Balance sheet
| Year ending | FY21 | FY22 | FY23 | FY24 | FY25 | FY26 |
|---|---|---|---|---|---|---|
| Equity capital | ₹24 Cr | ₹24 Cr | ₹26 Cr | ₹26 Cr | ₹26 Cr | ₹26 Cr |
| Reserves | ₹1.2k Cr | ₹1.2k Cr | ₹1.6k Cr | ₹1.9k Cr | ₹1.7k Cr | ₹1.7k Cr |
| Borrowings | ₹809 Cr | ₹1.5k Cr | ₹1.5k Cr | ₹1.4k Cr | ₹1.6k Cr | ₹1.7k Cr |
| Other liabilities | ₹547 Cr | ₹583 Cr | ₹618 Cr | ₹863 Cr | ₹1.1k Cr | ₹1.1k Cr |
| Total liabilities | ₹2.5k Cr | ₹3.3k Cr | ₹3.7k Cr | ₹4.2k Cr | ₹4.4k Cr | ₹4.5k Cr |
| Fixed assets | ₹1.3k Cr | ₹2.0k Cr | ₹2.8k Cr | ₹3.3k Cr | ₹3.0k Cr | ₹3.2k Cr |
| Capital work in progress | ₹517 Cr | ₹100 Cr | ₹99 Cr | ₹15 Cr | ₹316 Cr | ₹116 Cr |
| Investments | ₹0 Cr | ₹315 Cr | ₹0 Cr | ₹0 Cr | ₹0 Cr | ₹0 Cr |
| Other assets | ₹727 Cr | ₹886 Cr | ₹841 Cr | ₹983 Cr | ₹1.0k Cr | ₹1.1k Cr |
| Total assets | ₹2.5k Cr | ₹3.3k Cr | ₹3.7k Cr | ₹4.2k Cr | ₹4.4k Cr | ₹4.5k Cr |
How to read this
As filed each year. A line the company does not report — deposits for a non-lender, for instance — is left out rather than shown as a row of dashes.
Mutual funds in SAGCEM
Filings to Aug 2026
0 new, 0 added, 1 trimmed, 0 sold out — net −0.05 L shares (−0.1%).
- Held by funds
- ₹82 Cr
- 3 schemes
- Biggest holder
- SBI Multi Asset Allocation Fund
- ₹53 Cr · 0.3% of that fund
| Scheme | Holding | Last month | Held since |
|---|---|---|---|
| SBI Multi Asset Allocation Fund SBI Mutual Fund | ₹53 Cr | held | May '23 |
| HDFC Multi Cap Fund HDFC Mutual Fund | ₹23 Cr | −0.05 L | Dec '22 |
| SBI Comma Fund SBI Mutual Fund | ₹6 Cr | held | Dec '22 |
HDFC, Nippon India and SBI schemes, from their monthly disclosures. Changes are counted in shares, so a price move never looks like buying or selling.
Mutual funds Aug 2026
0 added, 1 trimmed — net −5,092 shares (−0.1%)
- Funds are sitting on
- -22%
- vs est. average cost
- Held by funds
- ₹82 Cr
- 3 schemes · ≈ 3.8% of the company
- Biggest holder
- SBI Multi Asset Allocation Fund
- ₹53 Cr · 0.3% of that fund
- Longest holder
- SBI Comma Fund
- 3y 9m · since Dec '22
Shares held by these funds +68%
Aug '23 50.01 L shares Jul '26
All earnings calls (5)
Read the Q1 FY27 call →Learn to analyse Sagar Cements Limited
Guides on how to read this kind of business and the numbers that matter.