MMFL MM Forgings Q2 FY27 results (Jul–Sep 2026) and concall
Management summary
- MM Forgings delivered a strong operating performance in Q2 FY27 with revenue of ₹551 crores and EBITDA of ₹110 crores (19.7% margin).
- A richer machining mix of 65% and higher sales realizations..
- H1 turnover reached ₹978 crores on 44,000 tons of volume, complemented by a ₹54 crore post-tax profit on a ₹64.29 crore land sale.
- While the company is on track to cross ₹2,000 crores in revenue for FY27 and ₹2,400-2,500 crores in FY28, commissioning of its flagship 16,500-ton press has been delayed to Q4 FY27 with SOP in Q1 FY28.
Source: Inve concall analysis and management guidance record.
Highlights
-
Q2 sales volume grew to 24,200 tons from 19,700 tons in Q1, bringing H1 sales to 44,000 tons and turnover to ₹978 crores
-
Machining mix rose significantly to 65% from 56%, driving sales realization to ₹2.23 lakh per ton
-
Average cost of debt decreased sharply from 8.5% last year to 5.42%, lowering Q2 finance costs from ₹21 crores to ₹19 crores
-
Capacity expanded from 120,000 to 130,000 tons following the addition of a 4,000-ton press at the Viralimalai plant
What they filed
Q2 FY27: revenue up 42.4%, net profit up 155.6% against the same quarter last year.
| Line item | Q3 FY25 | Q4 FY25 | Q1 FY26 | Q2 FY26 | Q3 FY26 | Q4 FY26 | Q1 FY27 | Q2 FY27 |
|---|---|---|---|---|---|---|---|---|
| Revenue | 364 | 355 | 349 | 384 | 405 +11% | 413 +16% | 420 +20% | 547 +42% |
| EBITDA | 73 | 72 | 63 | 67 | 72 −1% | 78 +8% | 75 +19% | 106 +58% |
| Net profit | 32 | 36 | 22 | 18 | 26 −19% | 48 +33% | 92 +318% | 46 +156% |
How to read this
₹ crore, as filed. The percentage beside a figure is the change against the same quarter a year earlier — never the quarter before, which would make every seasonal business look like it collapses and booms each year.
Guidance & targets
2Volume
Sales Volume H2 FY27 Volume · H2 FY27 · High confidence 50,000 tons
Annual Sales Volume FY27 Volume · FY27 · High confidence 90,000-95,000 tons
Source: Inve Guidance Tracker — management targets and direct quotes from the earnings call transcript.
Q&A highlights
216,500-ton heavy press commissioning delay and cost escalation Direct
I am happy to say first there are no cost escalations other than possibly interest... the delay of about six to eight months is because the foundation required big plates that needed to be welded and brought in. The execution of that from the vendor took more time than anticipate
Clarifies reason for delay of the flagship ₹240 crore heavy press line and confirms commissioning in Q4 FY27 with SOP in Q1 FY28.
Asked by Nipurn Khemka
Capitalization pace and low ROCE concerns (~10%) Partial
The 16,500 ton press itself is INR240 crore. That line itself. So that remains as a big chunk... I would have been concerned had we stayed put at previous levels this year also. But now that we have come out of the so-called rut that we were two years back, and we have started de
Analyst challenged management on spending ~₹800 crores over 3 years while capitalizing only ₹380 crores amid subdued ROCE.
Asked by Nipurn Khemka
Unlock risks & concerns, Q3 FY27 watchlist, and full call analysis
You’re reading a preview. Opening the full call uses 1 concall credit and unlocks:
- 8 risks, concerns & management red flags
- 5 watchlist triggers for Q3 FY27
- +6 more guidance targets & verbatim management quotes
- +6 more analyst Q&A exchanges & evasion checks
- Capital allocation & full section-by-section narrative
Sign in to use your monthly call allowance.
Inve summary of a publicly available earnings call transcript; see how call summaries are prepared and our regulatory disclaimer. · Share on WhatsApp · Scorecard image